Title Page
-
Conducted on
-
Please select and move forward
-
Prepared by
-
Site ID
-
VUE Work Order Number
-
What is Outside Air Temp
-
What is the Delta T
-
Verify the unit Thermostat is accurate and operating properly and replace batteries if needed.
-
Unit Type
- Packaged AC
- Packaged HP
- Gas Pack
- Chiller
- Boiler
- Water Source HP
- Cooling Tower
- Roof Top Unit
- Other
-
Unit Name/# (for example, the second package unit would be named PKG-02)
-
Inspect cabinet for signs of rust, wear or failure
-
Inspect all wiring and connections for tightness, signs of overheating, discoloration or compromise of wire insulation
-
Create an action item, and self generate work order, to address deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Inspect for refrigerant and oil leaks
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Does this unit have an economizer installed?
- Yes
- No
-
Inspect Mechanical linkages for wear, tightness, and clearances
-
Lubricate all motors and bearings if applicable
-
Straighten Condenser Coils
-
Verify smooth operation of compressor and fans
-
Record rated and actual fan and compressor running amps
-
Record suction and discharge pressures (enter N/A if not applicable)
-
Is this unit equipped with discharge and supply air temperature sensors and control devices?
-
Verify operation of these sensors
Evaporative/Blower Section
-
Straighten evaporator coils (up to 10% of the surface area)
-
Check fan cleanliness; inspect wheel, shaft and cage for wear and clearance.<br>Check sheaves and pulleys for wear and alignment.<br>Check belt for tension, wear, cracks, and/or glazing.
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Ensure TXV bulb is securely mounted and distributor tubes are protected from vibration and rubbing.
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Check motor starter if applicable
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Clean and flush evaporator drain pan, P trap and drain line. Ensure drain is adequately sized, has proper slope and support
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Replace air filter with MERV 8 filter or appropriate media
-
Write the date with permanent marker on filter frame. LEED BRANCHES REQUIRE MERV 13 FILTERS
-
Gas Heat?
-
Visually inspect heat exchanger for rust, pitting, and holes
-
Check supply air stream for presence of combustion gasses using a combustion gas analyzer
-
Inspect combustion air or induced draft fan and clean and lubricate if required
-
Verify operation of combustion air flow proving device (Vacuum, manifold or pilot)
-
Verify operation of flame detection device (thermocouple, thermopile, bi-metal)
-
Verify operation of high limit and rollout switches
-
Verify integrity of flue system
-
Verify operation and sequence of gas valve and burner controls
-
Verify proper gas pressure to the unit or manifold
-
Inspect gas line for leaks rust or needed repairs
-
Electric Heat?
-
Inspect all wiring and connections for tightness, signs of overheating, discoloration or compromised insulation
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Verify operation of resistive heating element
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Check and record voltage and amperage draw and compare to rating of heater
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Check for proper operation of controls, safeties, high limit switches etc. calibrate if necessary
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Heat Pump?
-
Verify proper operation of reversing valve
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Verify proper operation of defrost cycle
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Verify proper operation of auxiliary heat if applicable
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Does unit have a Variable Frequency Drive?
-
Verify proper operation
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Clean heat sink
-
Verify proper DC buss voltage
-
Are there VAV or Fan power units?
-
Inspect all wiring and connections for tightness, signs of overheating, wiring insulation compromised or discoloration
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Check linkages for wear, tightness, and clearance
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Verify fan cleanliness, inspect wheel, shaft and cage for wear and clearance
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Verify sequence of operations as applicable
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Verify operation of fan and motor
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Verify valve/actuator operation
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Check and record voltage and amp draw of resistive heating elements and compare with rating of the heater
-
Check and adjust controls, safeties, high limit switches etc. as needed
-
Replace air filter with MERV 8 filter
-
Write the date on filter frame in permanent marker. LEED branches require MERV 13 filters.
-
Does the site have any pumps that support HVAC operations?
-
Check for leaks on the pump and seals
-
Check inlet and outlet pressures
-
Ensure all drain and weeps are free and clear
-
Lubricate motor and pump bearing as required
-
Record rated amps and actual amp draw
-
Verify smooth operation of pump
-
Are there any unit ventilators or make up or air only units?
-
Inspect unit for cleanliness
-
Check dampers for wear, security. linkage adjustments
-
Clean condensate drain pan, P trap and drain
-
Inspect Fan cleanliness, inspect wheel, shaft and cage for wear and clearance
-
Check sheaves and pulleys for wear and alignment
-
Replace Belt
-
Check operation of fan switch
-
Check operation of low temperature safety device
-
Economizer and power exhausts, inspect linkages, motors, and seals calibrate as necessary
-
Boilers? Gas and #2 oil
-
Blow down feed water mud drums
-
Check and test blow valve and level float if applicable
-
Open fire side for cleaning and inspection
-
Check heating surfaces for corrosion, pitting, scale, blisters, bulges and soot
-
Visually inspect refractory for large cracks, broken pieces, or exposed metal
-
Check expansion tank and drain if needed
-
Clean fire inspection glass
-
Perform hydrostatic test if required
-
Check valves, supply piping and solenoids for leaks
-
Replace fuel nozzles
-
Inspect, clean and function test flame scanner and relay
-
Clean and adjust ignition electrode
-
Verify operation of burner fan air flow switch if applicable
-
Inspect and clean burner assembly, fan, blast tube, intake and dampers
-
Verify operation of firing rate motor
-
Inspect flue and barometric damper
-
Preform combustion test and adjust burner for maximum efficiency. Record: firing rate , fuel air ratio, CO2, CO, NOX
-
Perform smoke test
-
Test safety relief valve
-
Verify proper Delta T through boiler
-
Inspect and clean low water cutoff safety device and feed controls
-
Inspect all hot water/steam coils and valves for cleanliness and leaks
-
Steam Traps?
-
Inspect and clean strainer
-
Inspect and clean precipitate drum
-
Check trap for proper operation
-
Gas and Electric Unit Heaters, Heating Only units?
-
Check general condition of unit
-
Verify fan, fan guards, and louvers are tight and securely mounted
-
Create an action item and self generate work order repair deficiencies and escalate any out of scope items to property manager, provide detailed notes on all actions taken
-
Inspect flue barometric damper
-
Verify clean burner assembly
-
Light pilot (if applicable) and fire heater; verify proper flame, combustion air and flue operation
-
Lubricate fan motor if applicable
-
Verify proper operation of temperature control, pilot, high temperature and fan safety devices
-
Inspect all wiring connections for tightness, signs of overheating, discoloration or compromised insulation
-
Verify fan cleanliness; inspect wheel, shaft and cage for wear and clearance
-
Check sheaves and pulleys for wear and alignment
-
Replace Belt and tension properly
-
Fire Dampers?
-
Remove fusible link
-
Check operation of damper mechanism ensure it moves freely and closes fully
-
Reset damper, lubricate damper track and replace fusible link
-
Provide label or tag indicating damper was tested including date.
-
Is this unit new and never been serviced before?
-
Please complete the Retail HVAC Assessment Survey