Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location

PROJECT:

  • Project

  • Location

  • Client

VERIFICATION

  • Construction drawings approved for use

  • DRW

  • REV

  • PVC or HDPE

SET OUT

  • Set out by Builder / Surveyor

  • Co-ordination with other trades

EXCAVATION:

  • 1. Marked out per drawing

  • 2. Excavation to correct depth

PIPE WORK:

  • 1. UPVC SN6 Solvent cement joints

  • 2. Pipe install as per drawing

  • 3. Pipe install min 600mm depth to correct inverts

  • 4. Pipe bedded on select aggregate

  • 5. All pipework completed in area

  • 6. Lay identification / marking tape as required

  • 7. Pipe size used

BACKFILL

  • 1. 10mm Agg or bedding sand around pipe

  • 2. Backfilling trench with dirt

  • 3. Compaction of backfill material

TESTING:

  • 1. Air Pressure Test

  • 2. Hydrostatic Test

  • 3. Vacuum Test

  • Inspection (Fair Trading or Other as required)

COMMISSIONING:

  • All pipework pressure checked for leaks

  • All debris flushed from system

  • All air bled from system

  • Trench compactor used

  • Trench compacted in 150mm layers

REINSTATEMENT OF FINISHED SURFACE:

  • 1. Grass areas repaired

  • 2. Concrete areas repaired

  • 3. Asphalt areas repaired

2. Sign Off

  • CHECKED BY:

  • SIGNATURE:

  • DATE:

  • REVIEWED BY:

  • DATE:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.