Title Page

  • Work Order

  • Address
  • Valve Set type being installed at location

  • Conducted on

  • Prepared by

  • ServiceStream are responsible for planning, supply, and installation of the metro valve installation program. This program goes towards decreasing the number of properties that experience 3 or more unplanned interruptions in a rolling 12-month period by decreasing the number of shut off blocks across the state with more than 50 property connections
    Standard construction methodology applies for the installation upgrade, including, preparation, traditional excavation, pipelaying, fittings, backfill, compaction and reinstatement

Pre-Construction Completed : Item 2

  • Pre-start completed?

  • All required documentation is on site (SWMS : Overarching ITP : Drawings : Planning Prompt : Permits etc)?

  • All team members have relevant and current licences and tickets?

  • All Plant and equipment safety checks / PPE / Hand Tools checked?

  • All pipe : fittings and materials on-site fit for purpose and checked?

  • Tool Box completed?

Construction : Item 3

  • Traffic Management Plan established and in place? Photo of TMP plan and site required

  • Pre excavation site picture

  • Level 4 confirmed isolation is complete in readiness for construction? (Permit to be completed in JAMS)

  • Cut and excavate to required width and depth.

  • Is metallic pipe being cut?

  • Plumb guard is in use.

  • Spray Disinfection of parts and materials prior to installation (TMI-5026-OP-0492)

  • Valve Set - Constructed

  • Valve Set - Installed

  • Thrusting complies with arrangement type and WSCM DWG-4005-30007-02

  • Set Chambers

  • Backfill Trench / Roadway-Backfill in accordance with WSCM DWG 4005-30003-01. Compliance with Section B of WSCM/AS 1289

  • Level 4 confirmed recharged at conclusion of construction? (Permit to be completed in JAMS)

  • Reinstatement dimensions provided to Greg Jesson

Site Close out : Item 4

  • Disposal of material and spoil in accordance with EPA standards

  • Site demobilised and left clean in readiness for line marking; cats eyes etc

  • Provide measurements (chainage) for red-line mark-up / GIS update here - including from reference point (ie branch etc)

  • Works completed in alignment with scope of works and drawings?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.