Groundworks / Backfill
-
01 Preliminaries
-
SWMS developed
-
Environmental Controls in place<br>(Erosion and sedimental control measures implemented)
-
Permit to excavate
- DBYD Service Location Search
- Onsite Service Location (Trained and Certified Locator)
- Permitted to be Signed off by Project Engineer before Commencement of Design -
Permit gained
-
02 Shoring and Benching
-
Is shoring / benching required (excavations over 1.2m)
-
HOLD POINT - Certificate from an structural and or Geotechnical engineer verifying design at least 5 working days prior to commencement.
-
Certificate signed off
-
Add signature
-
03 Excavation
-
Survey / Set-out of the extents of excavation completed
-
Survey marks in place<br>(During excavation &, backfilling survey marks/pegs must not be disturbed)
-
Excavation is carried out to depths, dimensions & levels as shown on the drawings
-
Drawing Number:
-
HOLD POINT - Inspection of foundation material
-
Conformity records for the levels & dimensions of excavation for each foundation member
-
Excavated material removed off site
-
Disposal Records