Title Page
-
Site conducted
-
Location
-
Member Name:
-
Work Order #
INSPECTION CHECKLIST
-
Date:
-
Intial Inspection:
-
Will in house crews be doing the work or contractors?
-
Have all pole and anchor locations been marked for OUPS to be called in (Including Road)
-
Will flaggers be needed?
-
How many flaggers will be needed?
-
Will special equipment items be needed for crew to perform this job?
-
Will Mats be needed?
-
Will off road machine be needed?
-
Will trash pump be required?
-
Will the duct rodder be needed?
-
Will blower be needed as well as string?
-
Is there any primary to be inspected?
PRIMARY TRENCH
-
Proper Depth (minimum 36")
-
Bottom Level (no humps in conduit)
-
Follows approved route
PRIMARY CONDUIT
-
Proper Size Conduit
-
Proper Schedule PVC / HDPE
-
90 Degree Sweeping Bends
-
(Maximum of 360 degrees - including risers)
-
Pull String Installed
PRIMARY BOX PADS/SWITCH BOXES
-
Installed at Approved Locations
-
Installed to Spec
SECONDARY TRENCH
-
Is there secondary to be inspected?
-
Proper Depth (minimum 36")
-
Bottom Level (no humps in conduit)
-
Follows approved route
-
NOT backfilled
SECONDARY CONDUIT
-
Proper Size Conduit
-
3" up to 350 MCM Triplex
-
Proper Schedule PVC / HDPE
-
90 Degree Sweeping Bends
-
(Maximum of 360 degrees - including risers)
-
Pull String Installed
METER BASE
-
Inspection Permit
-
Wired Correctly
-
Riser Pipe and coupler
-
Are there any obstructions to the conduit going from the meter base into the ground?
-
Proper Grounding
INSPECTION RESULT (Indicate with (x) below)
-
Inspection Result:
-
INSPECTOR: