Information

  • Document No.

  • Block M

  • Intex Facades

  • Conducted on

  • Prepared by

  • West elevation

Inspection check list

  • Are the hand brackets set out in correct locations in accordance with the specified drawing locations.

  • Are the vertical support rails set out in correct locations in accordance with the specified drawing locations.

  • Are the horizontal support rails set out in correct locations in accordance with the specified drawing locations.

  • Has the horizontal OCSI fire stop installed to the correct locations, in accordance with the drawing locations?

  • Has the correct Siderise tape been used on the OCSI in the correct locations??

  • Are the brackets that have been used to install the OCSI the correct locations? And the correct way round?

  • Have the vertical fire stop OCSI been installed in the correct locations in accordance with the specified drawings.

This inspection sheet confirms that the item or area detailed above is 100% completed in line with the current specification, drawings and pre agreed sample panels although still remaining the sub-contractors responsibility until practical completion has been achieved.

  • Signed on behalf of Sub Contractor

  • Signed on behalf of Main Contractor

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.