Information
-
Name of facility
-
Address
-
Conducted on
-
Name of client representative during the audit ( if applicable )
-
Report prepared by:
1. BACKGROUND INFORMATION
-
Where there are actionable defects identified during the review of the facility, these are to be identified and raised as budget bids immediately or passed to the asset owner as a 'Follow Up' if the asset is not managed by CP
All costs and response times are approximate and are for estimation purposes only -
GIS LOCATION
-
BD number if know
-
Approx. Gross Floor Area (m2) Note: external measurement of walls is acceptable
-
No. Of habitable floor levels
- single storey
- 2 storey
- 3 storey
- Roof greater than 3 storeys high
-
Building Type ( for insurance ) A-D A - Reinforced concrete walls, floor, frame, roof [eg bomb shelter!] B - Non-combustible walls, floor, frame, roof (Excluding reinforced concrete as in Type A) [eg tin shed with steel purlins] C - Non-combustible walls and roof but with timber frame and floors [eg tin shed with timber frame] D - Combustible frame, walls, roof [eg timber shed]
- A - Concrete Reinforced
- B - All steel etc.
- C - Steel and TImber
- D - All timber
-
General Comments
2. AUDIT DETAILS
-
Weather at time of audit
-
EXTERNAL PHOTO OF FACILITY - taken at time of audit
3. LAND & SURROUNDS
3. a) Access Driveways, Roads, Footpaths, signage and barriers
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a BMR
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© SCHEDULE BUILDER:
-
Do you want to undertake a Programmed build ?
-
No. Of boom gates or auto. roller doors
-
General Comments
3. b). Landscaping
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a BMR
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© SCHEDULE BUILDER:
-
Do you want to undertake a Programmed build ?
-
Area of grass approx.(m2)
-
Area of shrubs or trees approx.(m2)
-
Does the facility have any irrigation?
-
Are there any backflow prevention devices fitted (rpz's)?
-
General comments landscaping and irrigation
3. c). Exterior - Finishes/Painting (and any structural elements)
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a BMR
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© SCHEDULE BUILDER:
-
Do you want to undertake a Programmed build ?
-
No schedule required for this asset type
-
General comments exterior finishes and painting
3. d). Exterior Fire and Safety
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a BMR
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© SCHEDULE BUILDER:
-
Do you want to undertake a Programmed build ?
-
Is there a fire hydrant within the grounds of the facility ?
-
No. Of extinguishers
-
No. Of fire hose reels
-
Is there a safety shower?
-
General comments exterior fire and safety
4. ROOF ( including: sheets, gutters and downpipes and fascias )
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a BMR
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© PROGRAMMED BUILD:
-
Do you want to undertake a Programmed build ?
-
Is roof sheet cleaning required at least yearly ?
-
Is gutter / downpipes clearance required at least yearly ?
-
Provide details of issue and suggested cleaning frequency
-
Are there Whirley birds or roof penetrations ?
-
General comments on roof
π π GENERAL CONDITION RATING - Exterior Elements
-
Condition rating - Access driveways, roads and footpaths
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Condition rating - Barriers and signage
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Condition rating - Landscaping and irrigation
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Condition rating - Exterior finishes / painting ( including any structural elements)
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Condition rating - Roof sheeting, roof drainage and facias
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
5. INTERNAL COMPONENTS (Room by room)
-
Draw a sketch of the facility showing internal rooms. Orientate with north arrow. Number rooms from 1 to 99 to ref. against the following ...
-
Rooms (press 'add room' button to add more rooms)
****** ROOM NO. *******
-
Provide details on room location and current use
5. a) Fire & Safety Systems
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a BMR
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© PROGRAMMED BUILD:
-
Do you want to undertake a programmed build ?
-
No. Of extinguishers
-
No. Of fire hose reels
-
No. Of lay flat hoses
-
No. Of fire blankets
-
No. of heat or smoke detectors
-
No. Of illuminated fire EXIT signs
-
No. of fire doors
-
Is there an EWIS panel in this room?
-
Is there a fire booster pump for this facility ?
-
Is there an FIP in this room ?
-
Are there sprinkler valves in this room ?
-
General comments fire and safety
5. b) INTERIOR FINISHES / PAINTING
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a PORTAL REQUEST
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© PROGRAMMED BUILD:
-
Do you want to undertake a Programmed build ?
-
No schedule required for this asset type
-
General comments interior finishes and painting
5. c) TOILETS, SHOWERS, KITCHENS & General PLUMBING
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a BMR
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© SCHEDULE BUILDER:
-
Do you want to undertake a SCHEDULE build ?
-
No. Of exhaust / extract fans
-
No. Of water coolers connected to mains water
-
No. Of ice making machines
-
Is there a cold room ?
-
Is there a grease trap ?
-
Are there water circulation pumps and or sewerage pumps or macerators?
-
Provide description...
-
Is there a cold water supply at the facility ?
-
Is there a hot water supply to the facility ?
-
Provide details of supply i.g. Gas or electric boiler etc.
-
General comments plumbing
5.d) SERVICES
π§DEFECT DETAILS:
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a PORTAL REQUEST
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© SCHEDULE BUILDER:
-
Do you want to undertake a SCHEDULE build ?
-
MECHANICAL SERVICES:
-
No. Of split system aircons
-
No. Of box aircons
-
No. Of auto pedestrian doors
-
No. Of doors with self-closing mechanisms
-
ELECTRICAL SERVICES:
-
Is the space lit ?
-
Are there a number of lights not working that would indicate that a bulk lamp change is needed? If response is 'Yes' provide details in the following 'Comments' section
-
Is there a distribution board present ?
-
Distribution Board
Distribution Board no.
-
No. of RCDS
-
Is 'thermoscan' required for this DB ? (Generally if there is more than 1 dist. board, or there are large loads)
-
Provide justification here ...
-
Are there solar panels ?
-
No. Of panels
-
Is there a BMS ?
-
Is there a CCTV system ?
-
Is there a security system with battery backup ?
-
Provide details here and make note of BATTERY DATE
-
General comments on services
5 e) Major Plant
π§ DEFECT DETAILS
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a PORTAL REQUEST
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© SCHEDULE BUILDER:
-
Do you want to undertake a SCHEDULE build ?
-
MAJOR PLANT - ELECTRICAL
-
Is there a generator ?
-
MAJOR PLANT - MECHANICAL
-
Is there a GOODS lift ?
-
No. Of passenger lifts
-
No. Of chillers
-
No. Of package units
-
No. Of air handling units
-
No. Of cooling towers
-
General comments major plant
6. WHOLE FACILITY - MISC
π§ DEFECT DETAILS
-
Is there a MINOR defect ?
-
Enter MINOR defect (enter each defect separately)
π MINOR DEFECT ..
-
Take photo if nec.
-
Does this asset require FOLLOW UP to be raised ? If so, click on the ... Button here >
-
Raise a PORTAL REQUEST
-
Is there a MAJOR defect or one that needs programming ?
-
Enter MAJOR defect ( Enter each defect separately )
π π MAJOR DEFECT ..
-
Enter exact location, defect details and works required
-
Take photo
-
Works priority
- HIGH - Within 1 month
- MEDIUM - Within 6 months
- LOW - Within 1 year
- Programmed 1 to 3 Years
- Programmed 3 to 5 years
-
Approximate cost to set aside for works ...
-
Do any assets need a follow up inspection ?
π© SCHEDULE BUILDER:
-
Is there portable equipment present that should be subject to regular testing ?
-
Is there a permanent gas connection? ( I.e. hard plumbing to a boiler etc. Do not include BBQ type installations). Note: Can be bottled gas or reticulated.
-
General comments or inclusions to annual operating costs :
7. π π GENERAL CONDITION RATING for WHOLE FACILITY
-
Fire and Safety
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Interior finishes and painting
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Toilets, showers, kitchens and plumbing
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Services - mechanical
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Services - electrical
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
-
Major plant
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable
8. OVERALL CONDITION SCORE for whole facility
-
Condition Rating. Score
Good/Very good (20+ yrs) >110
Average (10-20 yrs). 70-100
Poor (5-10 yrs) 50-70
Very Poor (< 5 yrs). < 50 -
Provide actual score obtained here ...
-
Suggested condition rating .....
- VERY GOOD
- GOOD
- AVERAGE
- POOR
- FAILED/REDUNDANT
- not applicable