Information

  • Name of facility

  • Address

  • Conducted on

  • Name of client representative during the audit ( if applicable )

  • Report prepared by :

BACKGROUND INFORMATION

  • GIS LOCATION
  • Council Division

  • Fixed Asset Resister FAR number

  • Approx. Gross Floor Area (m2) Note: external measurement of walls is acceptable

  • Check the ASBESTOS register before undertaking inspection.

    Username: user@contractor.com
    Password: asbestos123
    http:/cairns-regional-council.herokuapp.com/sites/179

  • Does the register indicate that asbestos is present or are there asbestos stickers on the facility ?

  • ---- Ensure that any areas of work consider the possible presence of asbestos on any works ---

  • No. Of habitable floor levels

  • Building Type ( for insurance ) A-D A - Reinforced concrete walls, floor, frame, roof [eg bomb shelter!] B - Non-combustible walls, floor, frame, roof (Excluding reinforced concrete as in Type A) [eg tin shed with steel purlins] C - Non-combustible walls and roof but with timber frame and floors [eg tin shed with timber frame] D - Combustible frame, walls, roof [eg timber shed]

AUDIT DETAILS

  • Weather at time of audit

  • EXTERNAL PHOTO OF FACILITY - taken at time of audit

DEFECTS

  • ..... Are there any identified defects ?

  • Enter defect (enter each defect separately)

  • DEFECT No.
  • Enter exact location, defect details and works required

  • Add media

  • Works priority

  • Programmed work is for larger jobs only. Provide details and notes here and discuss with supervisor upon return

  • Does the defect require a review and estimation by a specialised contractor or building supervisor ?

  • --- An allowance of $300 should be provided for quotation

  • Allowance for works approximate range, subject to quote

  • NOTE: THIS SUM IS SUBJECT TO CHANGE DEPENDING ON QUOTATION

  • Allowance for works approximate range:

  • 🚦🚦🚦🚦🚦🚦For CRC use🚦🚦🚦🚦🚦🚦

  • Is the defect possibly an end user agreement issue ?

  • BFM to forward to the Service Provider and Property Team for advice

  • Provide the ref. number from automatic email returned from the portal, once defect has been entered if CRC responsibility to fund

  • Comments if requred

SCHEDULE BUILDER (SB)

EXTERNAL - Components

  • 7) Is there a fire hydrant within the ground of the facility ?

  • 8) No. Of emergency access ways which need to be kept clear - generally o/s of emergency escape

  • 9) No. Of extinguishers on outside of facility

  • 10) No. Of fire hose reels on outside of facility

  • 11) Is there a safety shower? NOTE: Also check if it is in date - yearly inspections required

  • 12) Is gutter / downpipes clearance required at least yearly ? ( indicated by presence of large trees and/or gutters full of debris )

  • Provide details of issue

  • Comments if requred

EXTERNAL - Finishes, painting of the fabric of the facility

  • Do the walls have a painted or stained finish that needs to be treated within the next 3 years ?

  • Provide details as either a defect (small patch) or a 'FOLLOW UP' (larger works)

    Indicate size of area concerned (m2)

  • Provide a representative photo or two if possible ...

  • Comments if requred

INTERNAL - Fire & Safety Systems

  • 15) No. Of extinguishers

  • 16) No. Of fire hose reels

  • 17) No. Of lay flat hoses

  • 18) No. Of fire blankets

  • 19) No. of heat or smoke detectors

  • 20) No. Of illuminated fire EXIT signs

  • 21) No. of fire doors

  • 22) Is there an EWIS panel in this room ?

  • 23) Is there a fire booster pump set for this facility?

  • 24) Is there a FIP in this room?

  • 25) Are there sprinkler heads in this room?

  • Comments if requred

INTERNAL - Fixtures, Fittings and Painting

  • Do the walls/ceilings have a painted or stained finish that needs to be treated within the next 3 years ?

  • Provide details of work, size of area and location. Consider if a patch is going to be acceptable or complete repainting

  • Provide a representative photo or two if possible ..

  • Comments if requred

INTERNAL - Services

  • Is there a distribution board present ?

  • 43) No. of push button type RCDS

  • Is 'thermoscan' required for this DB ? (Generally if there is more than 1 dist. board, or there are large loads)

  • 44) Provide justification here ...

  • Are there a number of lights not working that would indicate that a bulk lamp change is needed?

  • Provide details for a bulk lamp change

  • 48) Is there a Standby Generator Set?

  • Comments if requred

PEST Control

  • Is there a sticker on site that indicates pest control is up to date ? (Can usually be found in meter box or under kitchen sink)

  • identify last date noted

  • if provided, indicate what pest control was applied, i.e. termites, cockroaches etc.

  • 51) Are there timber components on site that would require periodic inspection for termite treatment?

  • Comments if requred

ENERGY CONSERVATION MEASURES

  • Are there any male toilets that are NOT dual flush ?

  • List the number of pedestals which are single flush and dual flush and where they are, e.g. 2 single flush, 1 dual flush in men's.

  • Number Of solar powered lights

  • Are there PV solar panels on the building?

  • Identify the number of panels or KW rating from distribution board

  • Are there any hot water / solar panels on the building?

  • Provide details of the number of box ac's and location

  • Are there any incandescent / tungsten lighting units?

  • Identify number of lights and general location

  • Comments if requred

MISCELLANEOUS

  • General comments or inclusions to annual operating costs for critical components or for compliance

GENERAL CONDITION RATING - Exterior Elements

  • Condition rating - Landscaping

  • Condition rating - Access driveways, roads and footpaths

  • Condition rating - Barriers, Fences and signage

  • Condition rating - External fire appliances

  • Condition rating - Exterior finishes / painting

  • Condition rating - Roof sheeting, roof drainage and facias

GENERAL CONDITION RATING - Interior Elements

  • Condition rating - Interior fixtures, fittings, finishes and general paint condition

  • Condition rating - Toilets, showers & kitchens.

  • Condition rating - Services

  • Condition rating - Major plant

OVERALL CONDITION SCORE for whole facility

  • Condition Rating. Score

    Very good (25+yrs) >90
    Good (20-25yrs). 75-90
    Average (10-20 yrs). 60-75
    Poor (5-10 yrs) 50-60
    Very Poor (< 5 yrs). < 50

  • Provide actual score obtained here ... and condition e.g. 'AVERAGE' etc.

  • Suggested LEVEL OF SERVICE based on inspection findings and scoreo

General comments on any issues or assets NOT already covered in the above

General comments on any Capital works requirements (works over $10K that will extend the life of the facility)

ENERGY CONSERVATION MEASURES - Any ideas for improvement ?

INDICATIVE COST - SUMMARY FOR COMPLETE ASSET

  • Summary if INDICATIVE Cost of undertaking all identified works, including any quotations required (Note that this estimate excludes the costs of any works that might arise as a result of any specialist quotations if identified in the report)

SUMMARY OF HIGH PRIORITY ISSUES IN ORDER OF HIGHEST RISK AND ANY GENERAL COMMENTARY

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.