Information
-
Title
-
Prepared by:
-
Certificate No:
-
Project:
-
Date:
-
Site:
-
Purpose of the Isolation
-
Method Statement No:
-
Risk Assessment No:
-
Switching Coordinator:
Safe Isolation Procedure
-
Isolation agreed with the client?
-
STOP! Do not carry out Isolation. Agree with client first.
-
Authorised by:
-
Is it Safe to Isolate?
-
STOP! DO NOT CARRY OUT ISOLATION, ensure that risk assessment have been carried out and risk reduced to medium level to allow safe isolation to be carried out.
-
Voltage present at supply terminals?
-
What procedure have been followed to ensure that the supply is isolated and can not be reinstated?
-
Load Removed?
-
STOP! Remove Load before proceeding.
-
Means of isolation OPENED and LOTO?
-
STOP! Ensure that the supply is Locked Off Tagged Off before proceeding
-
Correct operation of Voltage detection instrument proved against known source of supply?
-
Prove correct operation of the Voltage detection instrument !
-
Danger Voltage present between Line & Line?
-
Isolation UNSATISFACTORY ! Repeat all steps again!
-
Danger Voltage present between Line & Neutral?
-
Isolation UNSATISFACTORY ! Repeat all steps again!
-
Danger Voltage present between Line & Earth?
-
Isolation UNSATISFACTORY ! Repeat all steps again!
-
Danger Voltage present between Neutral & Earth?
-
Isolation UNSATISFACTORY ! Repeat all steps again!
-
Operation of Voltage detection instrument proved again against known source of supply?
-
Prove correct operation of the Voltage detection instrument !
Isolation Details
-
Equipment/Circuit/Area Isolated:
Item
-
Details:
-
Point of Isolation:
-
LOTO Method:
- Lock
- Tag
- Seal
- N/A
-
Lock No:
-
Re-energise prevention method used:
-
Photo:
-
Fuses Removed?
-
Fuses kept by?
-
Re-energise prevention method used:
-
Circuits Proven DEAD?
-
Isolation UNSATISFACTORY ! Repeat Isolation Procedure.
Confirmation
-
Recommendations and additional notes:
-
Photo
-
Photo
-
Isolation carried out & confirmed by:
-
Select date