Information
-
Project Name:
-
Project No.:
-
Date & Time
-
Prepared by:
-
Equipment Location:
-
System:
Isolator a
-
1.1 Specified manufacture isolator used
-
1.2. Isolator correct size (amps)
-
1.3 Isolator used with the correct quantity of poles
-
1.4 Isolator mounted at the correct height.
-
1.5 Isolator mounted within suitable distance & line of sight of connected appliance.
-
1.6 Suitable isolator mounting fixings used.
-
1.7 No holes drilled in isolator enclosure to effect the IP rating of the isolator
-
1.8 Suitable cable gland used & checked for tightness.
-
1.9 When isolator is installed externally, all gland entries will be only from the bottom so as to prevent water ingress.
-
2.0 All connected cable cores checked for tightness & without any copper strands showing.
-
2.1 Verify that the earth cable conduct is connected straight through the isolator.
-
2.2 Check functionally of the isolator ON/OFF.
-
2.3 Check isolator is labelled.
-
2.4 Check that all connected cables are tested & recorded on a separate test sheet.
-
2.5 Does the isolator need to be locked off until connected equipment is commissioned.