Title Page
-
Site conducted
-
Audit Title
-
Project Name
-
Conducted on
-
Prepared by
-
Location
QA Inspection
-
Instructions
-------------------
1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
2. Add photos and notes by clicking on the paperclip icon.
3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
4. Complete audit by providing digital signature.
5. Share your report by exporting as PDF, Word, Excel or Web Link
Tyvek Breathable Membrane System
-
Main Contractor:
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Elevation:
-
Level:
-
Comments:
STRUCTURE
-
Primary Structure handover complete.
-
Personnel
- Installer
- A2O
Tyvek Membrane
-
Membrane installed horizontally
-
Personnel
- Installer
- A2O
-
100mm overlap on horizontal joints <br>
-
Personnel
- Installer
- A2O
-
150mm overlap on vertical joints.<br>
-
Personnel
- Installer
- A2O
-
150 -300mm overlap dressed around corners.
-
Personnel
- Installer
- A2O
-
<br>Fix membrane with double sided Tyvek tape, including between overlaps.
-
Personnel
- Installer
- A2O
-
All membrane joints sealed with Tyvek tape.
-
Personnel
Helping Hand Brackets
-
-
Helping hand bracket sizes checked to ensure correct cavity depth.
-
Personnel
-
Brackets fixed with thermal isolator in place, using correct fixings, in accordance with fixing specification.
-
Personnel
Completion
-
Installer Signature:
-
A2O Signature:
-
Client Signature: