Title Page
Post-tensioning ITP Installation
-
Client
-
Post-tensioning ITP Installation prepared by
-
Project Name
-
Project Number
-
Level and pour number
-
Installation Date
-
Location
-
This Post-tensioning Inspection & Test Plan (ITP) must be completed for each installation on the project.
Post-tensioning Design and Drafting
-
Is this a design and construction project by SRG?
- This is a design and construct project by SRG.
- This is an install only project, with the design done by external engineers.
Check Anchorages
-
Select post-tensioning system size.
- 12.7mm
- 15.2mm
-
Are the anchorages positioned within tolerance, according to the drawings?
-
Are the anchorages secured to prevent displacement?
-
Are the same number of anchorages installed as per the drawing?
Coil Number/Tag Identification
-
Type in Coil Number 1
-
Type in Coil Number 2
-
Type in Coil Number 3
-
Type in Coil Number 4
Check ducting and strand
-
Have the correct number of strands been installed in each tendon?
-
Are tendons positioned according to the drawing?
-
Have tendons been profiled according to the drawing and secured?
-
Is there sufficient jacking length for stressing?
-
Have grout tubes been installed and secured?
-
Have duct joints and grout tubes and dead ends been sealed?
Anti-burst reinforcement
-
Has anti-burst reinforcement been installed to all tendons, at each end?
-
If anti-burst hasn't been installed, has the builder been informed? Type in the name of the person informed and the date and time.
Engineers Inspection
-
Has an inspection been received from the builder?
-
Have all items on the inspection report been completed?
-
SRG Leading Hand - I confirm the post-tensioning installation is complete and ready for a concrete pour.
-
Main Contractor