Title Page
-
Site conducted
-
Project
-
Conducted on
-
Prepared by
-
Location
-
Zone
VERIFICATION:
-
Construction drawings approved for use
-
Drawing Number:
-
Revision Number:
-
Pipe Material
-
Materials approved for use
EXCAVATION :
-
Marked out as per drawing
-
Excavation to correct depth
PIPE WORK:
-
Pipe install as per drawing
-
Are alterations to design required
-
Alterations approved by builder/designer
-
Alterations marked clearly on Asbuilt drawing
-
Pipe install min 600mm depth
-
All pipework completed in the area
-
Pipe size used
PITS:
-
Pit install as per drawing
-
Pit installed in correct location
-
Pit installed at correct R.L
-
Pit installed parallel with building
-
Inlets and outlets correctly sparged
BACKFILL
-
10mm Agg or bedding sand around pipe
-
Backfilling Trench with dirt
-
Compaction of back fill material
TEES / BRANCHES / JUNCTIONS
-
Install as per drawing
-
Install in correct location
TRENCH COMPACTION
-
Trench compactor used
-
Trench compacted in 150mm layers
-
Compaction testing required and under taken
REINSTATMENT OF FINNISHED SURFACE
-
Grass areas repaired
-
Concrete areas repaired
-
Asphalt areas repaired
COMMISSIONING
-
All debris removed from pits
-
All grates installed
-
All pipe work flushed and free from debris
-
CCTV inspection of new pipe work
COMMENTS
-
Comments:
DATE and SIGNATURE
-
Checked By:
-
Date:
-
Reviewed By:
-
Date: