Title Page
-
Site
-
Conducted on
-
Prepared by
-
Location
-
Local DNO Licence Area
-
DNO Substation ID
Description of Work Carried Out
General Periodic Inspection
-
Thermographic Inspection of the installation
-
Housekeeping within protection and control buildings
-
General Visual inspection of access and perimeter compound.
-
Inspection of state of oxidation and general painting of equipment.
Current and voltage transformers
-
Inspection of primary and secondary earth connections
-
Thermographic general inspection of transformer
Power & Auxiliary Transformers
-
Transformer Description
-
Transformer Serial Number
-
Make/Model
-
Number of Tap Change operations
-
Inspection of local temperatures, earthing connections, bushing, abnormal sounds
-
Inspection of general oil level and filters
-
Visual Inspection of general equipment (Buchholz, oil level, thermal image)
-
Thermographic analysis of Bushings connections, auxiliary tanks, Silica-gel breathings, etc.
-
Oil Sample taken
-
Furan Analysis
-
Replacement of Silica Gel and Oil filter
-
Indication check
-
General Transformer Condition Check/Paintwork
Disconnectors and Motor Controls
-
Inspection of earthing connections
-
Number of Operations
-
Statius Indicator
-
Inspection of Auxiliary Switches, local and remote signalling
-
On load Thermographic inspection
-
Heaters inspections and test
Circuit Breakers and Switchgear
Identification
-
Type
-
Make
-
Model
-
Serial Number
-
Inspection of earthing connections
-
Inspection vents entries, heating and ventilation
-
Status Indicator/Mimic Condition
-
Condition of Paintwork
-
Oil/SF6 Levels within correct limits
Additional Checks
-
Test transformer fans and pumps
-
Test Water Pump System if applicable
-
Condition of flood defence system
-
Run 132-33KV Transformer Auxiliary cooling up to<br>confirm correct operation
-
Test heating working correct within Auxiliary control<br>cabinet and Tap Changer control cabinet
-
Check SF6 Gas pressure on switchgear
-
Check Dehumidifiers / Air condition /Heating / pumps<br>within the Substation
-
Visual inspection of 132kV Lines/Apparatus/disconnectors.
-
Visual inspection of compound bonding/Earthing to<br>apparatus and continuity
-
Check and record any recent protection operations and<br>reset relays
Inspection Summary
-
Oil Samples Taken Y/N
-
Why was sample not taken
-
Silica Gel and Oil filter condition
-
Has Silica Gel Been Replaced
-
Comments:
Completion
-
Remedial Works Completed
-
Safety Concerns
-
Signature