Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
PPE Required
-
PPE for this task: Hard hat and safety glasses with side shield required for each worker on each job.
-
Additional PPE needed:
- Gloves
- Protective clothing
- Face shield
- Goggles
- Safety harness
- Respiratory protection
- Cones
- Caution tape
Hand Protection
-
1. The hands/fingers will be exposed to:
- Abrasions caused by friction/moving part(s)
- Contusion caused by falling objects
- Burns caused by extreme heat/cold
- Irritation caused by chemicals/flammables
- Shock by electricity
- Crushing injury caused by pinch points
- Punctures caused by sharp-pointed objects
-
2. Have you inspected materials or jagged edges, burns, slivers, rough or slippery surfaces?
-
3. Are you wearing jewelry or loose clothing that could be caught in moving machinery parts?
-
4. For this task, my hands/fingers will be protected by the following type of glove.
- Cloth
- Leather
- Metal mesh
- Electrician's
- Rubber/PVC/etc.
- Hot Work
Hazard Identification-Hazard Controls
-
Chemical Exposure
- Chemical OK'd
- SDS available
- Container labeled
- Barricades
- Verified vessel is empty
-
Lift Equipment
- Scissors lift
- Man lift
- JLG
- Proper anchor
- Harness
- Lanyard
- Barricades
- Handrails
- Safety chain
-
Slips, wet surfaces
- Clean surface
- Barricade
-
Trips
- Relocate
- Barricade
- Use alternate path
-
Falls
- Less than 4 feet
- More than 4 feet
- Access/Egress
- Construct platform
- Tie-off
- Move work to ground
- Fall restraint guard rails, short lanyard
- Ladders, scaffold, steps
-
Falling Objects
- Seecure objects
- Guarding, covers
- PPE
- Barricading
-
Hazards to others working in vicinity
- Communication
- Barricading
- Shielding
- Ventilation
-
Hazards from others working in vicinity
- Communication
- Barricading
- Shielding
- Ventilation
-
Fire, Combustible Materials/Explosion
- Remove materials
- Relocate work
- Shields
- Wet area
- Fire watch
- Isolation/LOTO
- Air testing/monitoring
- Fire extinguisher
-
Housekeeping
- Area kept clear of trash/debris
- Tools organized
- Hoses/cords out of path/rolled
-
Weather
- Possible winds shift
- Secure materials/equipment
- Line of fire - equipment and objects
- Consider stopping work in high winds
- Equipment erection-braced during construction
- Design specs reviewed
-
Heat/Cold Stress
- Ventilation
- Task rotation, shared tasks
- Work/rest regimen
-
Lifting, Pulling, Pushing
- Get equipment designed for the job
- Proper technique
- Smaller, lighter loads
- Prepared for "unexpected" release
- Move feet to turn with load
-
Repetitive Motion
- Proper technique
- Power tools rather than manual
- Get help, take breaks
- Seek advice
-
Rotating Equipment
- Isolation, LOTO
- Guarding, barricading
- No loose clothing
- Positioning
-
Pinch Point/Line of Fire
- Guarding
- Positioning
-
Sharp Objects
- Guarding
- PPE, gloves, etc.
- Positioning
-
Electrical Shock
- Isolation, LOTO
- Testing
- Grounding
- Shielding of equipment
- GFCI
- Electrically qualified
- Voltage __Procedure #, Min Clearance
-
Airborne/Flying Material
- Cover/shield source
- PPE< eye & face
- PPE, arms & body
- Positioning
-
Environmental Spill
- Containment
- Waste plan
- Waste containers
- Others
-
Confined Space
- Air mnitoring
- Ventiation needed
- Attendant required
- Asphyxiation
- Chemical hazard
- Electrical hazard
- Mechanical hazard
-
Thermal Burn
- Splash guard
- Isolation, LOTO
- Positioning
- Equipment covers
- Additional PPE
-
Cranes and Rigging
- Crane inspection
- Are lift weights known?
- Are slings and chokers inspected & correct sizes?
- Is crane lift area properly barricaded?
- Are operators certified to operate?
- Is wind speed known?
- Are personnel trained in proper rigging procedures?
- Are tag lines used to control all loads?
- Is a Critical Lift Plan needed?
- Rotating superstructure barricaded?
- Are mats/cribs in place on outriggers?
- Is a spotter needed when traveling?
-
Falls, falling objects
- Walk, use handrails on stairways
- Secure materials and tools
- barricade area below work
- Fasten chain on scissor lift
- Safe access to elevation
- Maintain three point contact when climbing
- Walking surfaces free of clutter, slip hazards
- Footwear in good condition
- Tie off above waist
- 5000 pound anchor (3" or larger)
- 100% protected above 4 feet
- Eyes looking in direction of travel
- rigged so doesn't contact level/object below
-
Food Safety
- 1. Will the scope of the work impact the food safety of the affected equipment?
- 2. Will the scope of the work impact the food safety of the surrounding equipment?
-
-
Is a permit required?
-
Is a procedure required?
-
Do you have the proper tools and/or equipment to do this job?
-
Are your tools and/or equipment in good condition? (I.e., inspected?)<br>
-
Have you planned your escape route?
-
Did you perform an on-site inspection with the permit issuer?