Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
FABRICATION
-
Job Description
-
Client
-
Contact name, phone, email
-
Date Scoped
-
SUPERVISOR (MEN)
-
SUPERVISOR (DAYS)
-
FITTER (MEN)
-
FITTER (DAYS)
-
BOILERMAKER (MEN)
-
BOILERMAKER (DAYS)
-
TRADES ASSISTANT (MEN)
-
TRADES ASSISTANT (DAYS)
-
BLAST/ PAINTER (MEN)
-
Deliver to Site
DESIGN
-
Engineering: Total hrs
-
Documentation: Total hrs
CONSUMABLES
-
undefined
-
undefined
-
undefined
-
undefined
SHS
-
25x25x2 - 6m
-
25x25x3 - 6m
-
40x40x3 - 6m
-
50x50x3 - 6m
-
50x50x5 - 6m
-
65x65x4 - 6m
-
65x65x6 - 6m
-
75x75x4 - 6m
-
75x75x6 - 6m
-
89x89x6 - 8m
-
100x100x6 - 8m
-
100x100x9 - 8m
EQUAL ANGLE
-
25x3 - 6m
-
25x5 - 6m
-
30x5 - 6m
-
40x5 - 6m
-
50x5 - 6m
-
50x8 - 6m
-
65x5 - 6m
-
75x6 - 6m
-
75x10 - 6m
-
90x6 - 9m
-
90x10 - 9m
-
100x10 - 9m
FLAT BAR - 6m
-
25x5
-
32x5
-
40x3
-
40x6
-
50x5
-
50x8
-
65x6
-
65x10
-
75x6
-
75x10
-
90x6
-
90x10
-
100x8
-
100x12
-
130x6
MILD STEEL PLATE 1200x2400
-
2mm
-
3mm
-
5mm
-
6mm
-
8mm
-
10mm
-
12mm
-
16mm
GALV PLATE 1200x2400
-
1mm
-
2mm
-
3mm
ALUMINIUM PLATE
-
3mm Gr5005
-
4mm Gr5005
-
5mm Gr5005
-
8mm Gr5005
-
10mm Gr5005
GALV WELD MESH 3000x2400
-
25x25x3.15
-
50x50x4
GRID MESH 1025x6000
-
C325MPG12
-
D325MPG12
-
F325MPG12
PFC CHANNEL - 9M
-
75
-
100
-
125
-
150
-
200
-
250
GALV PIPE
-
25nb Medium
-
32nb Medium
-
65nb Medium
-
80nb Medium
STANCHIONS/BENDS
-
32nb 90deg (Galv)
-
25nb 90deg (Galv)
-
32nb Closure Bend (Galv)
-
P Type' Stanchion (Galv)
-
P Type' Stanchion, Drilled One Side (Galv)
-
PC Type' Stanchion (Galv)
-
W Type' Stanchion (Galv)
-
S Type' Stanchion (Galv)
-
SC Type Stanchion (Galv)
-
SO Type Stanchion (Galv)
FIXINGS
-
M12
-
M16
-
M20
-
M24
-
M30
BLAST AND PAINT
-
FMG Blue
-
BHP Grey
-
Golden Yellow
-
PPA Grey
-
White
-
NDT:
INSTALL LABOUR
-
SUPERVISOR (MEN)
-
How many days
-
FITTER (MEN)
-
How many days
-
BOILERMAKER (MEN)
-
How many days
-
RIGGER (MEN)
-
How many days
-
SCAFFOLDER
-
How many days
-
COXSWAIN
-
How many days
-
DECKHAND
-
How many days
-
SPOTTER
-
How many days
-
CODED WELDER
-
How many days
-
Other:
PERMITS
-
Gas Test
-
Work at Heights
-
Confined Space
-
Isolations
-
Exclusive Control
-
Hot Works
-
Weld Procedures:
EQUIPMENT
-
Other
-
Diesel Welder – trailer - (Days)
-
Caddy Welder - (Days)
-
Mig / Tig Welder - (Days)
-
6Kva Gen Set - (Days)
-
Light Truck - (Days)
-
Mobile Lighting - (Days)
-
EWP - (Days)
-
Scaffold - (Days)
-
Crane – AT20 Franna - (Days)
-
Crane – Other - (Days)