Title Page
-
GeoOP job number
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
Solar Module Details
-
PV module manufacturer and model number
- Sunpower E20 327W
- Sunpower E20 345W
- Sunpower P19 320W
- Sunpower P19 390W
- Sunpower P19 395W
- Sunpower P19 400W
- Q-Cell G4 305W
- Q-Cell G5 270W
- Sapphire gem 275W
- Sapphire gem 300W
- Trina Honey 305W
- Trina Smart 275W
- Other
-
Number of solar modules
-
String configurations
Inverter Details
-
Inverter
-
Inverter manufacturer
-
Inverter model number
-
Inverter Serial Number
-
Number of MPPTs
Installation Checkoff
-
Array frame is certified to AS1170.2 for installation location
-
Array frame is installed to to manufacturers instructions
-
No galvanically dissimilar metals are in contact with the array frames or supports
-
Roof penetrations are suitably sealed and weatherproofed
-
PV wiring losses are less than 3% at the maximum current output of the array
-
Where PV array comprises multiple strings, string protection has been provided
-
Wiring is protected from mechanical damage and is appropriately supported
-
Weatherproof PV isolator mounted adjacent to array
-
All low voltage wiring has been installed by a licensed electrical tradesperson
-
All wiring has been tested and approved by a qualified electrical tradesperson
-
PV array isolator mounted adjacent to the inverter
-
Isolator is mounted on output of inverter
-
Lockable AC circuit breaker is mounted within the switchboard to act as the inverter main switch for the PV/inverter
- 16 Amp
- 20 Amp
- 25 Amp
- 32 Amp
-
Inverter is installed to manufacturers specification
-
Inverter ceases supplying power within 2 seconds of a loss of mains power
-
Inverter does not resume supplying power until mains have been present for more than 60 seconds
-
All labels are installed to CEC and Australian Standards
Continuity check
-
Continuity of all strings, sub-arrays and array cables
-
Continuity of all earth connections (including module frame)
Insulation resistance measurements
-
Array Positive to earth M ohm
-
Array negative to earth M ohm
System Commissioning check
-
String Test Results
String
-
String tilt and orientation
-
String polarity
-
Irradiance at time of testing
-
String measured Voc
-
String operating voltage
-
String measured Isc
-
String operating current
Anti Islanding Test
-
Time for inverter to disconnect is less than 2 seconds
-
Time for inverter to reconnect greater than 60 seconds
Installers Information
-
Name and CEC Accreditation number of Installer
- Kyle Schubert - A3956368
- Gavin Mascas - A6898487
- Chris van Zanten - A1575465
- Mark Doolan - A9768638
- Mitch Blatchford - A6073247
- Andrew Lyell
- Cameron Walker - A9975582
- Steve Lowe - A1930000
-
CEC Designer and Installers signature
-
Name and Licence of Electrician
- Kyle Schubert - A54184 - 75163S
- Gavin Mascas - A56033 - 299764C
- Chris van Zanten - A142103 - 293549C
- Mitch Blatchford - A47066 - 210055C
- Andrew Lyell - A59501 - 67294S
- Mark Doolan - A50178 - 68022S
- Cameron Walker - E37355 - 39795S
- Steve Lowe - A27128 - 286411C
-
Electricians signature