Title Page
-
Document No.
-
Project Name:
- Yes
- No
- N/A
-
Site/Location:
- Yes
- No
- N/A
-
Conducted on:
-
e-Builder Project Number (Format is CAP123456):
-
Project Superintendent:
- Yes
- No
- N/A
-
Project Foreman:
- Yes
- No
- N/A
-
Prepared by:
Open items from previous inspections
-
Open items:
-
Add media
-
Have all open items been corrected?
Personal Protective Equipment
-
Hart Hats
-
Eye/Face Protection
-
Hearing Protection
-
Respiratory Protection
-
Knee Pads
-
Foot Protection
-
Task Appropriate Gloves
-
Proper Clothing & Safety Vest
-
Personal Fall Protection
Daily ILSM/Housekeeping
-
Have ILSM measures been implemented
-
Dept. & contractors aware of project measures
-
Signs/barricades posted
-
Evacuation map
-
Access/egress clear of debris & materials
Daily Inspection/Use of Ladders
-
Ladders inspected/good condition
-
Task appropriate ladders being used
-
Extension ladders secured & 3' above landing
-
Guardrails/Open Hole Covers/Barriers
-
Guardrails inspected and secured
-
Floor/wall covers secured & adequate signs
-
Physical barriers inspected & secured
-
Trades aware of fall protection requirements
Daily Inspection of All Scaffolding
-
Scaffolds erected by Competent Person
-
Trades trained to use scaffold
-
Inspection tag posted & up to date
-
Secured to building or outriggers used
Fire Protection
-
Temporary fire protection in place/inspected
-
Has local fire department been notified
-
Trades trained in CODE RED procedures
-
Fire watch required today
-
Fire watch logs completed
-
Hot work/burn permit posted & signed
First Aid/Emergency Procedure
-
First aid supplies adequate for number of workers
-
Emergency numbers posted
-
Emergency procedures identified to workers
-
Eye wash kit on project
Electrical
-
Task lighting covers/cords in good condition
-
Power cords in good condition/construction grade
-
GFCI protection being used
-
Is there any exposed energized wiring/parts
Tools/Equipment
-
Staff trained to use tools/equipment
-
All cords/guards in good condition
-
Operating tools/equipment safely
-
P.A. tools/laser signs posted as required
Site/Public Environmental Safety
-
Emergency spill procedures in place
-
Spill kits/clean up equipment available
-
Proper storage/disposal of hazardous materials
-
Emergency shut offs & location identified
-
Excessive noise levels controlled
-
Impalement hazards properly covered
-
Temporary barriers in place
-
Exterior lighting/fencing adequate
-
Exterior project - warning signs posted
CPFC Project Broad Focus Items
-
SDS binder/inventory list readily available
-
Subcontractors compliant with Subcontractor Performance Safety Standards
-
Are safe work practices being followed
-
Project safety checklist signed by subcontractors/correct
-
CPFC Energized Electrical Program is followed
-
LOTO in place, adequate & verified
-
Any issues with Project Safety Checklist
-
ICRA level accurate to project phase/area
-
ICRA level being maintained
-
Is negative air machine log in place
-
Check Magnehelix - proper reading
-
Asbestos O&M program being followed
-
CPFC lead program being followed
-
Confined space procedures being followed
-
Heat illness - shade/drinking water at site
-
Has pre-task plan been completed
-
Is safe crane procedures bring followed; pre-lift plan, operator & crane certificates
-
Is safe excavation/trenching being followed; shoring, barricades, fall protection
Response required
-
Please correct all documented violations within 5 business days upon receipt of this notification. In response to this report you will need to provide documentation of all corrections. Documentation shall be provided in the form of pictures, uploaded via e-builder to the appropriate folder. This report also addresses all repeat violations that have been identified in previous inspections and have yet to be corrected. Repeat findings will continue to be documented until they are corrected and closed out. Please contact me via telephone or e-mail if you have any questions.