Information
-
Work Order / Service Request Number
-
Date and Time of Audit
-
Site Address
-
Is this required for this audit? SECTION A (Where audit is only to be conducted on external plant hired then go to SECTION B)
- Yes
- No
SECTION A - can be used for Council works that includes Council employees and /or contractors working for Council under minor works or tender. (if an audit is only to be conducted on external plant hired then go to SECTION B)
-
Person in Charge:
-
Personnel on site:
-
Activity at site:
SECTION A - Audit
-
1 - Has a worksite Job Risk Analysis been conducted?
-
JRA Date:
-
JRA Work Order Number:
-
JRA Location:
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
2 - Has the Job Risk Analysis been conducted in consultation with affected employees, subcontractors and OH&S representatives on site?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
3 - Pre-start checklists filled out & being returned weekly?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
4 - Plant operators competent: CCF Card (or like), relevant motor vehicle licence sighted?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
5 - Required PPE worn by all on site: including appropriate sun protection?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
6 - Person in charge has current traffic management accreditation.
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
7 - Traffic management plan / procedure developed for work at this site/or for this activity - has it been sighted?
-
TMP Date:
-
TMP Work Order Number:
-
TMP Location:
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
8 - On site traffic guidance scheme installed as per traffic management plan / procedure?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
9 - Changes to TMP / procedures recorded?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
10 - Speed limit used?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
11 - Speed limit relevant?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
12 - Traffic flowing smoothly?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
13 - Are there delays occurring?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
14 - Vehicle mounted warning devices operational?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
15 - All plant free of obvious leaks and defects?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
16 - Traffic controllers being used?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
17 - Traffic controllers appropriately positioned?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
18 - Traffic controllers currency of competency?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
19 - Be prepared to stop signs used with traffic controllers?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
20 - Traffic signals being used (mobile lights)?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
21 - Advance warning signs used?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
22 - Correct location / positioning of advance warning signs?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
23 - Other warning and regulatory signs used and appropriately positioned?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
24 - Inappropriate signs covered?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
25 - Road condition signs required?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
26 - Road condition signs placed?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
27 - All sign mounting systems secure?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
28 - Delineators in good order and placed appropriately?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
29 - Work area / work site delineated appropriately?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
30 - End works / speed limits reapplied?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
31 - Long term after hours traffic management?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
32 - After hours procedure or plan developed?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
33 - After hours plan available to view?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
34 - Traffic management scheme effective?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
35 - Traffic guidance scheme check frequency.
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
36 - Site free of controllable hazards?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
37 - All hazards considered in traffic management plan?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
38 - Other?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
Is this required for this audit? SECTION B (To be used for all external plant hired. If already identified in Section A then Refer Section A column)
- Yes
- No
SECTION B (To be used for all external plant hired. If already identified in Section A then Refer Section A column)
-
Person in charge:
-
Personnel on site:
-
Plant item 1
-
Plant type?
-
Make?
-
Model?
-
Rego?
-
Plant item 2
-
Plant type?
-
Make?
-
Model?
-
Rego?
-
Plant item 3
-
Plant type?
-
Make?
-
Model?
-
Rego?
-
Plant item 4
-
Plant type?
-
Make?
-
Model?
-
Rego?
SECTION B - Audit
-
39 - Has the Job Risk Analysis been sighted by the operator?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
40 - Pre-start checklists filled out & kept in vehicle?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
41 - Plant operators competent: CCF Card (or like), relevant motor vehicle licence sighted?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
42 - Plant operators White Card?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
43 - Required PPE worn by all on site: including appropriate sun protection?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
44 - Traffic management plan / procedure developed for work at this site/or for this activity - has it been sighted by the operator?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
45 - Vehicle mounted warning devices operational?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
46 - All plant free of obvious leaks and defects?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
47 - Insurance Certificates of Currency current & on file?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
48 - Plant Items Risk Assessments held on file?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
-
49 - Other?
-
Items to be rectified and resolution if resolved during the audit:
-
Attach photo or other if applicable
-
Due by?
References
-
Traffic Act 1925
-
Tasmanian Traffic Control at Work Sites Code of Practice June 2004
-
AS1742.3
-
Disability Service Act 2011
-
Workplace Health & Safety Regulations 2012
-
Traffic (Road) Rules Regulations 1999
-
General Specs and Conditions of contracts by DIER and local authorities
-
Workplace Health & Safety Act 2012
-
Roads and Jetties Act 1935
Additional comments?
-
General comments:
Section A - Signed by person in charge of site
-
Person in charge:
Section B - Signed by person in charge of plant / site
-
Person in charge:
Signed Off By Auditor
-
Auditor:
Email to: Manager/Coordinator in charge for review i.e. first name.last name@launceston.tas.gov.au CC to: Safety Compliance Officer - aussie.dukeson@launceston.tas.gov.au
Manager/Coordinator Action
-
1. Review and take any action if required
2. Forward email and audit onto Safety Compliance Officer - aussie.dukeson@launceston.tas.gov.au acknowledging action already taken at the time of the audit and advising what action will be taken for outstanding non compliances.
Safety Compliance Officer Action
-
1. Arrange CRMs if required and action has not already been taken.
2. Forward audit onto Infrastructure Operations Manager advising CRMs have been raised - matthew.millwood@launceston.tas.gov.au
Manager Infrastructure Operations Action
-
Email remountroad.admin@launceston.tas.gov.au with approval to register to SF5926