Information
-
Site/crew
-
Manager
-
Supervisor
-
Conducted on
-
HSE Tech/Prepared by
-
Location
Site Arrival
-
JSA filled out properly
-
Is there handwritten input?
-
Are persons trained for their individual tasks
-
Proper warning signs posted at entrance
-
All personnel in proper PPE
-
All personnel trained and certified for their specialized operation
-
Location has designated smoking area
-
Wind sock Available?
-
Additional Comments
Tree
-
Flanges have all bolts and are the correct size and properly torqued and tested
-
All valve handles are correctly installed for proper use
-
Valves capable of venting to atmosphere are capped & a means of bleed off installed.
-
Tree pressure tested at shop to maximum anticipated pressure/ API standard
-
Verify that the # of turns to (FULLY) open/close each valve and choke are written on the wellhead and are correct
-
Additional Comments
Flow Lines
-
No threaded connections leak upstream of choke manifold
-
All flow iron upstream of choke must be tested to 10k and 5k downstream of choke banded/identified every 6 months
-
Break apart ALL threaded connections and visually inspect before EVERY flow line installation
-
Tested to maximum anticipated pressure + an acceptable safety margin or working pressure
-
Unions are positioned correctly for direction of flow & checked for compatibility
-
Lines are not bowed or laid in a bind
-
Additional Comments
Flow Line Restraints
-
Have personnel who install restraints received training, if so by whom?
-
Set as not to cause excessive dips, arches, or bows in flow lines
-
Set first Flow Line Restraint as close to wellhead as feasible placing one every joint- upstream of manifold every other joint- downstream of manifold with hammer union positioned between the Flow Line Restraints.
-
On flow lines, are all angels and unions tied down from the wellhead to open-top tanks
-
Additional Comments
Manual Chokes
-
When completely closed- reading is 0/64
-
Pressure test body to same pressure as flow line
-
Housing and seat checked prior to flowing of Well
-
Additional Comments
Flow Back Tank/ Gas Buster
-
Clean sand prior to transport
-
Set level must be in conjunction with transfer pumps.
-
Tanks grounded
-
Trucks using bonding cables
-
Adequate fall protection or tie-offs(built in or portable platforms if properly secured will suffice)
-
Easy access for tank gauging, walkways and stairs should not be damaged or missing pins
-
External valves not in use have barrier device installed in case of accidental opening
-
Set to provide easy truck access for hauling out produced fluids
-
Working wind sock installed near tank
-
Additional Comments
H2S
-
H2S plan provided for well that may exceed 10 PPM
-
H2S site specific procedures developed for location (if required)
-
H2S contingency plan on location (if required)
-
H2S plan is coordinated by safety department and implemented by foreman
-
Additional Comments
-
Add media
Sign Off
-
Signature
-
On site representative