Title Page
-
Name of auditor carrying out Electrical QA post inspection
-
Date of inspection
-
Inspection location
-
Scope of electrical works that have been carried out at this location?
- Cyclical Electrical Testing
- Empty Homes Electrical Works
- Electrical Responsive Works
- Full Electrical Rewire
- Smoke Alarm Installation
- Other
-
Give a brief description of works carried out
-
Contractor who carried out the works
- Livv Maintenance
- Elect Building and Maintenance
- All Safe Trades
- UPS Building and Maintenance
- Cannon Elec
-
Operative who carried out the works
-
Initial works completion date
-
Livv Housing Group job number
Visual Inspection
-
Is there any damage to service cut out/metering equipment?
-
Has this been reported to DNO/energy supplier?
-
Does the earthing system match what is identified on the certification?
-
Are the main protective bonding conductors in place and adequately sized?
-
Are the meter tails adequately supported?
-
Does the consumer unit have all required labelling/notification on it?
-
Does the consumer unit have all required blanks in place and meet the minimum IP requirements?
-
Is there any evidence of thermal damage within the consumer unit?
Electrical Inspection and Testing
-
Has the relevant electrical certification been issued and completed correctly?
-
Is the measured Zdb and PFC satisfactory for the type of earthing system in place?
-
Has this been reported to the DNO?
-
Please inform DNO immediately
Socket Circuit
-
Are the electrical power outlets/accessories visually in an acceptable condition?
-
Are the readings recorded by the electrician within acceptable tolerance of what is measured today by the auditor?
Lighting Circuit
-
Are the lighting accessories visually in an acceptable condition?
-
Are the readings recorded by the electrician within acceptable tolerance of what is measured today by the auditor?
-
Does the RCD trip within 300ms and does the test button operate the device?
Cooker Circuit
-
Are the cooker outlets visually in an acceptable condition?
-
Is the electrical wiring from the cooker outlet to the cooker connection to an acceptable standard?
-
Are the readings recorded by the electrician within acceptable tolerance of what is measured today by the auditor?
-
Does the RCD trip within 300ms and does the test button operate the device?
Shower Circuit
-
Is the shower unit and isolation switch visually in an acceptable condition?
-
Is the isolation switch in the correct wiring zone as defined within special locations in BS7671?
-
Are the readings recorded by the electrician within acceptable tolerance of what is measured today by the auditor?
-
Does the RCD trip within 300ms and does the test button operate the device?
Other Circuit
-
Circuit designation
-
Are the electrical accessories that are part of this circuit visually in an acceptable condition?
-
Are the readings recorded by the electrician within acceptable tolerance of what is measured today by the auditor?
-
Does the RCD trip within 300ms and does the test button operate the device?
Smoke Alarm Installation (Only to be completed if the property has received a full LD2 upgrade)
-
Are all detectors installed in the correct locations?
-
Are the CO detectors installed in the correct locations?
-
Has a smoke alarm control unit been installed in a suitable location?
-
Do all detectors sound when test button is pressed?
Customer Satisfaction
-
Was the customer kept informed of the works to be completed?
-
Did the electrician identify themselves with ID badge before starting works?
-
Did the electrician keep the property clean and tidy whilst carrying out the works?
-
Please report to Electrical Managers.
-
Was the customer happy with the works that were carried out?
-
Give a brief description of why the customer is unhappy with the works carried out
-
Please report to Electrical Managers.
-
Are there any further comments from the customer?
Post Inspection Summary
-
Does the auditor have any other observations or recommendations to report?
-
Does the auditor have any further comments?
-
Outcome of Electrical QA post inspection
-
Auditor Signature