Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

PREVIOUS INSPECTION

  • Has the last inspection been reviewed

  • Are there no outstanding issues

SITE RECORDS

  • Site specific safety plan on site and available<br>

  • LFS JSA Completed Prior to Work & reviewed with employees

  • Contractor JSA completed prior to work & reviewed with employees

  • Hot work permit obtained from client prior to work

  • MSDS onsite and available

  • LFS Morning safety meeting performed

GENERAL

  • Adequate distance from overhead power lines (minimum 10 feet)

  • Hazard signs displayed

  • Adequate lighting provided

  • Muster location identified

  • First aid kit available

  • Eyewash kit available

  • Guy wires flagged

  • Vehicles out of guy pattern

  • Good overall housekeeping

  • Emergency numbers displayed in doghouse

  • Designated smoking area provided

  • Pump location (exhaust)

  • Spacing/return tanks/pump/all engines

  • Authorized Personnel signs posted

  • H2s controls in place if applicable

GUYING

  • Crown to ground guy lines in place

  • Adequate number of wind guys

  • Condition of wires

  • Correct diameter of lines

  • Three clamps/turnbuckle minimum

  • Ground anchors

  • Tubing board guys in place

  • Tubing board guys strung and crossed for racking

  • Internal guys adjusted for tension

  • Outriggers in place and pinned

FOUNDATION

  • Drill rig erected on stable ground

  • Outriggers fully extended with stabilizing pads

  • Stabilizer pads on place on mats (wood)

HAND TOOLS

  • All wrenches checked for wear and defects to prevent slippage

  • Damaged or defective tools tagged and taken out of service

  • Proper tools used for task at hand

MAST/DERRICK

  • Ladder condition

  • Tubing board condition

  • Manual latch dog extension/retraction mechanism

  • Scoping ram stabilizers

  • Crown-Sheave Guards

  • Finger board safety chain in place

  • Derrick locking pins in place with safety pins

DOGHOUSE

  • Adequate exits, doors installed properly, operate freely

  • Approved heaters used

  • Emergency phone numbers posted

  • Proper postings posted

  • Good housekeeping

  • Electrical/lights in good working condition

  • Two-Way radio provided

  • First Aid station located in Dog house

CARRIER

  • Guardrails/handrails on elevated walkways and steps

  • Head, tail and signal lights working

  • Wheels chocked

  • Condition of tires and wheels

  • Fuel tanks labeled

  • Exhaust system

  • No loose or flammable materials stored in cab

  • Glass and mirrors

  • Windshield wipers

  • Hydraulic leveling jacks secured by mechanical locknuts

  • Brakes/Emergency

DRAWORKS CONDITION

  • Guards in place

  • Tubing and drilling line condition

  • Sufficient wraps left on drum with blocks in down position

  • Deadline anchor and retainer

  • Cathead line divider/gap

  • Catline condition

  • 3 wraps on drill line

  • Tubing/sand line brakes condition

OPERATOR STATION/WORK PLATFORM FLOOR

  • All controls labeled

  • Work floor

  • Rotary table area fully guarded, floor level, non-skid material, areas from of mud, holes

  • Vee door gate provided, in place, secured with chain or other safety device

  • Steps/handrails

  • Safe access provided

  • All gauges functioning properly

POWER TONGS CONDITION

  • Tong door

  • Stiff arm. snub/safety line

  • Tong hose disconnects

  • Tong positioner

  • Tong body and jaws operate freely, latch properly, clean, no welds

TRAVELING ASSEMBLY CONDITION

  • Blocks

  • Sheave guards/lock

  • Bales/links

  • Elevators/air slips

BLOWOUT PREVENTER (BOP)

  • BOPs installed, tested and functional

  • Wheels and stems in place

  • BOP properly stabilized to keep full stack centered over blowhole

  • All lines connected to close BOP, no leaks, protected against damaged

  • All unused BOP and accumulator lines plugged or capped

  • BOP unit kept clean, free from mud, ice build up, tools, adequate drainage provided

RIGGING EQUIPMENT

  • Rigging equipment inspected prior to use

  • Nylon chokers free of tears, holes, cuts, burns, discoloration and snags

  • Chains inspected and have identification tag stating size, grade, rated capacity and sling manufacturer.

  • Wire rope slings are free of broken wires ( 5 broken wires in one strand in one rope lay), kinking, crushing, corrosion and birdcaging

  • Labels visible and legible on rigging equipment

  • Shackles free of damaged such as bent, twisted, distorted, stretched, elongated, cracked, nicks, pitting and corrosion

  • Tag line used to control the load

PIPE RACK AREA

  • Ends of pipe racks chocked

  • Pipe racks level and stable

  • Pipe rack catwalk clear of debris and material

  • Stair and handrail provided for cat walk

  • Vee door slide free of holes, pipe stops used on catwalk or slide

  • Employees not walking on top of pipe

MUD PUMP AREA

  • Drive belts, pony rods guarded

  • Ends of relief lines secured

  • Head and valve covers fully bolted

  • General Housekeeping around mud pit area clean of debris and material

  • Approved and adequate lighting in area

MUD MIXING AREA

  • Bagged material properly stacked

  • General housekeeping in area

  • Adequate ventilation in area

  • Approved and adequate lighting in area

MUD TANKS AND PITS

  • Adequate stairs with handrails provided

  • Guardrails provided on crossover

  • Shale shaker guarded

  • Mud guns and jetting hoses secured

  • Adequate lighting in area

  • General housekeeping

GENERATOR AREA

  • Generators properly located

  • All generators moving parts guarded

  • HIGH VOLTAGE warning signs used

  • All electrical tools grounded

  • Hearing protection available

  • General housekeeping and lighting

  • Electrical wires properly strung and protected

FUEL STORAGE TANKS

  • Fuel storage tanks properly located

  • All storage valves marked as to connects

  • Stationary ladders on storage tanks

  • All fuel storage tanks properly labeled

BARRICADES

  • Protective barricades (cable rope, wooden post and rail, ect) are provided and used to warn and protect personnel

  • Highly visibility yellow caution tape or red danger tape used to alert personnel to hazards

SAFETY EQUIPMENT/PRACTICES

  • Geronimo line in place/anchored

  • SRL fall protection device in place

  • Safety harness, lanyard provided at tubing board, rod basket and stabbing board

  • Derrick ladder climbing device provided

  • Fire extinguishers in place?

  • Flammables in U.L. safety cans

  • NO SMOKING rules enforced

  • Flare area clear of combustibles

  • Welding performed safely

  • Personal protective equipment in use or available ( hardhat, safety glasses, steel toe boots, gloves, ear protection)

  • FRC clothing worn

  • H2S equipment in use

  • Emergency kill switches available

Forklift Operations

  • Employee qualified to operate forklift

  • Has proper inspection be performed prior to use

  • Seat belt worn when operating

  • Other

SIGNATURE

  • On site representative

  • Auditor's Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.