Cleaning Audit

Female Changing Areas

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • DRAINS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • SINKS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Male Changing Areas

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • DRAINS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • SINKS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Ground Floor Corridors

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Buffer Hold / Buffer Change and Transfer Areas

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Buffer Prep

  • FLOORING - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

EFH / Facility B Change Areas and Interlocks

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

EFH / Facility B

  • FLOORING -Is the 4 stage Biocide Clean being carried out 1 day per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 6 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • DRAINS - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SINKS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

SWFH Change Areas

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

SWFH

  • FLOORING -Is the 4 stage Biocide Clean being carried out 1 day per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 6 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1day per week?

  • DRAINS - Is the 1 stage Biocide clean being carried out 7 days per week?

  • SINKS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

NWFH (All rooms)

  • FLOORING -Is the 4 stage Biocide Clean being carried out 1 day per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 6 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1day per week?

  • DRAINS - Is the 1 stage Biocide clean being carried out 7 days per week?

  • SINKS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Purification Change Areas / Interlocks and Corridors

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Suites 1 / 2 / 3

  • FLOORING - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • DRAINS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • SINKS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Purification (+5) Cold Rooms

  • FLOORING - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SURFACES / DOORS - Is the 1 stage Biocide clean being carried out Once a Month?

  • Take photo of current page of Log Book for this area.

Consumable Store

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Bulk Fill Prep Areas

  • FLOORING - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SURFACES / DOORS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Bulk Fill Cold Areas

  • FLOORING - Is the 1 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Bulk Fill Change and Transfer Areas

  • FLOORING - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Bulk Fill

  • CAMPAIGN - Is the 1 stage Biocide clean taking place 1 day per week or between every product batch?

  • FLOORING - Is the 1 stage Biocide clean taking place 1 day per week or between every product batch?

  • SURFACES / DOORS - Is the 1 stage Biocide clean being carried out on each day of area use?

  • Take photo of current page of Log Book for this area.

Facility E Transfer and Change Rooms

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Facility E

  • FLOORING - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • DRAINS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • SINKS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

West Staircase

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

First Floor Corridor

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Cleaning Storage Areas

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

MST Areas

  • FLOORING -Is the 4 stage Biocide Clean being carried out 1 day per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 6 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • DRAINS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • SINKS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Autoclave Loading Room

  • FLOORING - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Wave Area, Inoculum Change and Transfer Areas

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • SINKS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Inoculum Suites and Media Prep

  • FLOORING - Is the 2 stage Biocide clean being carried out 7 days per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 1 day per week?

  • SINKS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Consumable Store & QC Equip Room

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Dispensary (+5C) Cold Rooms

  • FLOORING - Is the 1 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

  • FLOORING - Is the Once a Month Sweep/Vacuum and Sanitise with Klercide 70/30 taking place?

Dispensary (-20C) Cold Rooms

  • FLOORING - Is the Once a Month Sweep/Vacuum and Sanitise with Klercide 70/30 taking place?

  • SURFACES / DOORS - Is the 1 stage Biocide clean being carried out 1 day per week?

  • Take photo of current page of Log Book for this area.

Cell Banking Change Area /Interlock Rooms

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Cell Banking Dewar, QA Office and Lobby Areas

  • FLOORING -Is the 4 stage Biocide Clean being carried out 2 days per week?

  • FLOORING - Is the 2 stage Biocide clean being carried out 5 days per week?

  • SURFACES / DOORS - Is the 4 stage Biocide clean being carried out 1 day per week?

  • SURFACES / DOORS - Is the 2 stage Biocide clean being carried out 2 days per week?

  • Take photo of current page of Log Book for this area.

Other Areas (please list)

  • Add question?

Health & Safety

  • Is the Cleaning Equipment clean and tidy throughout the Manufacturing Area?

  • Take photo of last entry of the cleaning machine Log Books

  • Are all PSS Staff wearing the correct PPE for the areas in question?

  • Have stock levels been audited, are there sufficient on site?

Management Sign Off

Management Sign Off

  • Premium Representative Sign Off

  • Client Representative Sign Off

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.