Site Name
-
Prepared by
-
Conducted on
-
Personnel
Indoor installation
-
Baseband screws tightened
-
Baseband connected to earth
-
SFP 65/2 connected to 1800 and 47/2 connected to 800
-
DC cables well connected to SPDs
-
Fiber optic cables labeled
-
EC bus cable labeled(From both sides)
-
RRUs power cables labeled (SPD and PDU/Breaker side)
-
Baseband power cable labeled (From both side)
-
Winder boxes labeled (Band and Sectors)
-
Zoomed out photo of the cabinet
-
Zoomed in photo of the baseband installaltion
-
Photo of the SPDs
-
Photo of DC breakers/PDUs
Outdoor installation
-
RRUs are installed as per the standard (IF NOT, fill in the Advised by)
-
Advised By:
-
RRUs are connected to earth
-
Earth kit for DC cables is done
-
Fiber and DC cables installed on cable clamps
-
DC and Fiber cables are installed separately
-
Earth cables are well tightened
-
800 jumpers are connected to antenna ports and well tightened
-
1800 jumpers are connected to antenna and well tightened
-
Jumpers are well isolated (Down to Up)
-
Power cables are well isolated
-
Fiber optic cables are labeled
-
DC cables are labeled
-
Cable tray is closed with metallic tie-wraps
-
Zoomed out photo of sector 1
-
Zoomed IN photo of sector 1
-
Zoomed out photo of sector 2
-
Zoomed in photo of sector 2
-
Zoomed out photo of sector 3
-
Zoomed IN photo of sector 3
-
Photo of cable tray
-