Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Front Elevation Photo

  • Fire Alarm Panel

  • Fire Alarm Panel - Make, Model and Location

  • ABM

  • Main Contractor

  • Project Start Date

  • Project Completion Date

  • Handover Date

  • Parking Available on Site

Pre Project Information

  • Fire Risk Assessment - All works to be completed to MAB standard

  • Outlet Fact File - All information up to date?

  • Site Security - Safety Lampholders, Lighting linked to Intruder alarm.

  • Licensing Drawing - is the drawing up to date?

  • CMI report - - All works to be completed to MAB standard

  • Mitie Report - - All works to be completed to MAB standard

  • Asbestos - Site report available?

  • Asbestos - is a new report required for the proposed works?

  • LED - Has this site had a complete LED conversion

  • FMR - is the report available

  • FMR - are there any FMR works required?

  • Duct Cleaning Report - - All works to be completed to MAB standard

Kitchen

  • Gas Interlock - Is one fitted - is it operational

  • Gas Solenoid - details & gas pipe size

  • Lighting - General condition of all light points

  • Small Power

  • IP Rated socket fitted under the dishwasher area

  • Mechanical - General condition of taps, waste and pipe work

  • Fire Alarm

  • Kitchen Ventilation

  • Other

Rear / Kitchen Yard

  • Lighting

  • Outside tap

  • External socket for washer

Dry Store

  • Lighting

  • Fire Alarm

  • Ventilation

  • Other

Back of House

  • Lighting

  • Small Power

  • Ventilation

  • Mechanical

  • Fire Alarm

  • Other

Cellar

  • Lighting

  • Small Power

  • Glycol Timers - are they installed - are the times correct

  • Fire Alarm

  • Ventilation

  • Mechanical

  • Other

Bottle Store

  • Lighting

  • Small Power

  • Fire Alarm

  • Ventilation

  • Mechanical

  • Other

Staff Room

  • Lighting

  • Small Power

  • PIR detection for lighting & ventilation

  • Fire Alarm

  • Ventilation

  • Mechanical

  • Other

Staff Toilets

  • Lighting

  • Small Power

  • PIR detection for lighting and ventilation

  • Fire Alarm

  • Ventilation

  • Mechanical

  • Other

Boiler Room

  • Lighting

  • Small Power

  • Fire Alarm

  • Ventilation

  • Boilers - general condition - make & model

  • Water Heaters - general condition - make & model

  • Pressurisation Units - general condition - make & model

  • Heating Controls - labelled and working correctly

  • Fluing

  • Other

Cleaners Cupboard

  • Lighting

  • Small Power

  • PIR Detection for lighting and ventilation

  • Fire Alarm

  • Ventilation

  • Mechanical

  • Other

Laundry Room

  • Washing Machine - MAB Spec

  • Tumble Drier - MAB Spec

  • Timer for tumble drier

  • Lighting

  • Small Power

  • PIR detection for lighting & ventilation

  • Fire Alarm

  • Mechanical

  • RCD Socket/Plug top - is one fitted

  • Other

Managers Office

  • Lighting

  • Small Power

  • Fire Alarm

  • Mechanical

  • Ventilation

  • Air Conditioning

  • Other

Glasswash

  • Lighting

  • Small Power

  • IP Rated socket fitted under the glass washer area

  • Fire Alarm

  • Ventilation

  • Mechanical/ Plumbing

  • Other

Trading Area

Back Bar

  • Lighting

  • Small Power

  • Coffee Machine - does it need disconnecting & reconnecting

  • Plumbing

Bar Area

  • Lighting

  • Small Power

  • Fire Alarm

  • Ventilation - do the fans need cleaning - are they operational

  • Heating - are all the radiators operational - do the TRVs operate

  • Fire Places - is there a spark/fire guard fitted - are they operational - what type installed

  • Air conditioning - is it operational

  • Other

Lounge Area

  • Lighting

  • Small Power

  • Fire Alarm

  • Ventilation - do the fans need cleaning - do they operate

  • Heating - are all the radiators operational - do TRVs operate

  • Fire Places - is there a spark/fire guard fitted - are they operational - what type is installed

  • Air conditioning - is it operational

  • Other

Restaurant Area

  • Lighting

  • Small Power

  • Fire Alarm

  • Ventilation - do the fans need cleaning - are they operational

  • Heating - are all the radiators operational - do the TRVs operate

  • Fire Places - is there spark/fire guard fitted - are they operational - what type is fitted

  • Air conditioning - is it operational

  • Other

Salad Cart

  • Is small power OK

Carvery Deck Area

  • Carvery Supply

  • Heat Lamps

  • Ventilation

  • Lighting

  • Small Power

  • Other

Customer Toilets

Gents Bar Toilets

  • Lighting

  • Small Power

  • Ventilation

  • Mechanical/ Plumbing - Sparge Pipes, Urinal Waste, Traps, Float, Cistermiser, Urinals, Toilets (inc flush handles & seats)

  • Other

Ladies Bar Toilets

  • Lighting

  • Small Power

  • Ventilation

  • Mechanical/Plumbing - Toilets, Cisterns (inc flush handles), Toilet Seats , Taps

  • Other

Gents Restaurant Toilets

  • Lighting

  • Small Power

  • Ventilation

  • Mechanical/ Plumbing - Sparge Pipes, Urinal Waste, Traps, Float, Cistermiser, Urinals, Toilets (inc flush handles & seats) Taps

  • Other

Ladies Restaurant Toilets

  • Lighting

  • Small Power

  • Ventilation

  • Mechanical/Plumbing - Toilets, Cisterns (inc flush handles), Toilet Seats' Taps

  • Other

Disabled Toilet

  • Lighting

  • PIR- are these required for lighting & ventilation

  • Small Power

  • Ventilation

  • Mechanical/Plumbing - Toilets, Cisterns (inc flush handles), Toilet Seats,Taps

  • Disabled Alarm - is it operational - audible in the bar - pull cord suitably located

  • Other

Meeting / Function Rooms

  • Lighting

  • Small Power

  • Fire Alarm

  • Ventilation

  • Heating - are all the radiators operational - do the TRVs operate

  • Air Conditioning - is it operational

  • Other

Store Rooms / Void Rooms

  • Lighting

  • Small Power

  • PIR detection for lighting & ventilation

  • Fire Alarm

  • Ventilation

  • Mechanical

  • Other

Main Entrance

  • Lighting

  • Small Power

  • Switching - is staff final exit switching required

  • Other

Other Entrances

  • Lighting

  • Small Power

  • Switching - is staff final exit switching required

  • Other

Staff Accomodation

  • Lighting

  • Small Power

  • Fire Alarm

  • Ventilation

Front Elevation

  • Lighting

  • Signage

  • Other

Side Elevations

  • Lighting

  • Signage

  • Other

Rear Elevation

  • Lighting

  • Signage

  • Other

Beer Garden

  • Lighting

  • Smoking Shelter

  • Heat Lamps

  • Jumberellas

  • Outside Plumbing

  • Other

Roof

  • Adequate lighting for servicing purposes

  • Adequate access for servicing purposes

  • Ventilation Plant

  • Air Conditioning Pant

  • Local isolation fitted to all plant

  • Is edge protection required

Car Park

  • Lighting

  • Signage

Outbuildings

  • Lighting

  • Small Power

  • Fire Alarm - is it linked to main system

  • Ventilation

  • Mechanical

  • Other

  • Project Manager Sign Off

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.