Partition QA first fix
-
Select date
-
Wall location. N / E / S / W ?
-
Setting out correct?
-
Specify stud type / centres and correct size to spec ?
-
Tap con fixings at correct centres ?
-
Timber nogging to back of gyp-liner for fixing ?
-
Celotex installed and correct size ?
-
Noggins correct and fitted in accordance with builders work request?
-
Opening and jambs and heads correct.?
-
VCL Installed correctly with a minimum of 150mm overlap ?
-
Correct board and fixings and screw centres, and where applicable boards correctly staggered?
-
Correct sealant/ mastic used?
-
Tape and joint above ceiling completed
-
Works accepted by for MDL
-
Snags to be rectified, photos attached
-
Works accepted by client/ builder
-