Information
-
Document No.
-
Audit Title
-
Client / Site
-
Description of plant
-
Make and Model of Plant
-
Asset ID (If applicable)
-
Conducted on
-
Prepared by
-
Location
-
Personnel
1.0 Plant Hardware Condition
-
1.1 Are all moving parts (belts, pulleys, sprockets, chains and shafts that could expose workers to machinery entanglement, adequately guarded?
-
1.2 Are all catwalks in good condition on the main conveyors?
-
1.3 Are all silos caps in place and locked?
-
1.4 Are all overhead bins properly lined and in good shape?
-
1.5 Are overhead Agg gates operating correctly and in good shape?
-
1.6 Are steps and hand rails on plant adequate and situated to allow safe access and egress?
-
1.7 Are hydraulic hoses and fittings in good condition with no leaks?
-
1.8 Are PTO master shields, shaft and PIC guards in place and good order and condition?
-
1.9 Are there any air leaks that can be heard and are need of repairs?
-
1.10 Are all instruments and gauges functional and in good working order?
-
1.11 Are all E-STOPS working properly?
-
1.12 Are all lock-out and limit switches in good working order and fitted where necessary?
-
1.13 Are all silo dust collectors working properly?
-
1.14 Is pant and equipment fitted with tag-out systems and physical lock-out mechanisms; that prevent the accidental energising or starting of plant and machinery when maintenance or repairs is being performed?
-
1.15 Are all main dust collectors working properly?
-
1.16 Are all Reclaimer stations functioning as they should., pump, switches pipes?
-
1.17 Are all silo screws working as they should?
-
1.18 Does any silos need painting?
-
1.19 Are all silos clearly marked with their content?
-
1.20 Are all slump stands functioning as they should and in safe condition?
-
1.21 Are all scales functioning as they should?
-
1.22 Are all water systems working as they should?
-
1.23 Are all air systems working as they should?
-
Are there any additional finds not reported above?
3.0 Plant Electrical Systems
-
3.1 Is the adequate lighting at all slump stands?
-
3.2 is there proper light in the loading area?
-
3.3 Is there spare blubs for replacing burn out lighting?
-
3.4 Is there any expose wire any where on the Plant site?
-
3.5 Are there fire extinguisher in place near electrical systems?
-
3.6 Does the Plant operator have FPL phone number support line onsite?
-
3.7 Is fuel system on site properly working.. Veeder Root or Gas boy pump?
-
3.8 Are all electrical breaker boxes labeled and secured?
-
3.9 Are all exit signs working properly?
-
3.10 is there proper lighting at the reclaimer area?
-
3.11 Do signals work for loading complete .. Traffic light or horns?
-
3.12 Is the main disconnect to the plant functioning ?
-
3.13 is the main disconnect labeled?
-
3.14 Are all energy hazards label?
-
Are there any additional finds not reported above?