Information
-
Document No.
-
Client / Site id
-
Conducted on
-
Location
-
Commissioning engineer
-
Restrictions made by end user (eg access and performance of tests)
-
Date of completion/handover
-
Is the system type appropriate and as specified?
-
What category is the system?
-
Is a BAFE certificate available?
-
Were the certificates provided in the correct time frame?
MAINS SUPPLIES
-
Is this a dedicated circuit?
-
Is continuity of supply satisfactory?
-
Is labelling satisfactory?
-
Non-RCD protected?
-
Wiring protected against fire and, if appropriate, mechanical damage?
-
Current rating of supplies sufficient for full alarm load?
CONTROL & INDICATING EQUIPTMENT
-
Are company logo/phone number labels on the CIE?
-
Is positioning appropriate?
-
Is there an emergency light within 2m of CIE?
-
Is this suitable security over access to controls?
-
Is a zone plan displayed?
-
Does the Control Panel provide correct text display? (Addressable only)
-
Does the control panel provide adequate zone LED display?
-
Is the internal wiring and workmanship satisfactory?
-
Are all cables labelled?
-
Does the mains 230v cable enter seperately?
-
Is the correct rated fuse installed in the fuse spur?
-
Is fuse spur correct type? ie only isolatable by special tool.
ADDITIONAL CONTROL PANELS/REPEATERS
-
Are the appropriate aspects of the above section satisfactory?
STAND-BY POWER SUPPLIES
-
Is the internal wiring and workmanship satisfactory?
-
Are the batteries of a suitable type?
-
Are the battery capacity calculations available?
-
Have the quiescent and alarm currents been used in the calculations?
-
Is the battery capacity adequate?
-
Is the wiring to any separate battery enclosure of a suitable type?
-
Are all batteries properly secured and dated?
-
Does the mains 230v cable enter seperately?
-
Is the correct rated fuse installed in the fuse spur?
-
Is fuse spur correct type? ie only isolatable by special tool.
WIRING
-
Does the area per loop satisfy the installation rules?
-
Is there adequate short-circuit isolation i.e. each zone partition and every 20 detectors? (Addressable only)
-
Are the locations of short circuit isolators appropriate? (Addressable only)
-
Does short and open circuit fault operate correctly?
-
Does head removal fault operate correctly?
-
Does removal of a detector result in isolation of any manual call point?
-
Are there spurs on any circuits?
-
Are cables of suitable type and adequately protected against fire?
-
Are cables adequately protected against mechanical damage?
-
Is each Incoming cable (eg from control panel end) To each point suitably identified and earths sleeved and continued through?
-
Are all junction boxes suitably marked with fire alarm label?
-
Is this suitable segregation from other services and, where appropriate, between fire alarm system cables?
-
Is there evidence to show that circuit parameters e.g. resistance and capacitance satisfy manufacturers recommendations?
-
Are insulation resistance test results available and satisfactory?
-
Are cables suitably supported?
-
Is the cable correct type and colour?
-
Are cable penetrations fire stopped?
VISUAL AND AUDIBLE ALARMS
-
Are there are at least two sounder circuits? (Unless loop based sounders are used)
-
Is this satisfactory evidence that sound levels have been measured and found to be sufficient?
-
Is the sound level likely to interfere with the summoning of the Fire Brigade? (E.g. reception phone near sounder)
-
Does the sound pattern and frequency comply with the installation rules? (e.g. Bells not mixed with sounders)
-
Is there a need for visual\vibrating alarms in areas which these are not present?
DETECTORS
-
Are the types of detector used appropriate?
-
Is detector siting and spacing appropriate?
MANUAL CALL POINTS
-
Are call point locations and sitings appropriate?
-
Are call points mounted at the appropriate height?
ZONING
-
Is the area per zone within the limits specified in BS5839?
-
Is the search distance within the limits specified in BS5839?
-
Are remote indicator lamps provided where required by BS5839?
-
Are zone boundaries appropriate for the fire compartments?
REMOTE TRANSMISSION OF ALARMS
-
Is there a method for remote transmission of alarms?
-
Is the enclosure the correct type?
-
What is the signal strength of the Dualcoms GPRS?
-
Does the signalling system provide the appropriate signals (e.g. Pin 1 fire \ Pin 2 fault) back to the ARC?
-
Is the wiring of a satisfactory type?
ANCILLIARY SERVICES
-
Are there any ancillary services\equipment interfaced with the fire alarm system?
-
Is the method of interfacing of a satisfactory type?
-
Is any power required from the fire alarm system within its limits?
-
Are ancillary circuits separately fused?
SERVICING AND SPARES
-
Is there a contract for servicing? (Specify why, if not)
-
Are appropriate spares held on site? (E.g. Spare break glasses)
DOCUMENTATION
-
Is the cause-and-effect operation noted for this installation?
-
Is there satisfactory logbook?
-
Does the logbook have variations written in in?
-
Is there a satisfactory certificate, indicating all variations from BS5839?
-
Are there satisfactory as fitted drawings? (Wiring diagram)
-
Are there satisfactory manuals onsite?
COMPLETION OF AUDIT
-
Follow up required?
-
Brief description if follow up required.
-
Engineers signature
-
Auditor signature