Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Add signature
1. HSE Management and Induction
-
1.1 Copy of HSE Policy and Project/Site HSE plan available at site and Communicated to all workers
-
1.2 Risk assessments completed and recorded
-
1.3 Fredon induction undertaken by all workers (include SWMS)
-
1.4 Principal Contractor Induction undertaken by all workers
-
1.5 Induction records kept for each person
-
1.6 PPE and safety equipment issued and recorded
-
1.7 Site rules issued and recorded
-
1.8 Monthly HSEQ reports completed and submitted
2. Daily Pre-start Meetings
-
2.1 Pre-Start meetings held daily
-
2.2 Records of attendance kept and minutes kept
-
2.3 SWMS and Identified risks are included
3. Tool Box Meetings
-
3.1 Tool box meetings held weekly or as specified in HSEQ Plan
-
3.2 Records of attendance kept and minutes kept
-
3.3 Suggestions and issues are investigated and resolved
-
3.4 Input from workers, subcontractors, customers and project management
4. Consultation and Representation
-
4.1 HSE consultation arrangements in place (eg HSE reps)
-
4.2 Workplace HSE committee operating at site
-
4.3 Minutes of HSE committee meetings posted on notice boards
-
4.4 HSE representatives/committees inspect the site
-
4.5 HSE representatives/committee members receive training
5. Competency and Certification
-
5.1 Workers engaged in ‘prescribed’ occupations are certified and records kept
-
5.2 Licences/Competencies recorded in register, copies of certificates kept
-
5.3 Personnel who are being trained are supervised
6. Safe Work Method Statements (SWMS)
-
6.1 SWMS are developed, reviewed/specific for the job and registered
-
6.2 Task steps and High Risks Hazards identified and included
-
6.3 SWMS include adequate Control Measures
-
6.4 Communicated and necessary training/instruction received by all workers
-
6.5 Workers comply with controls in SWMS and procedures
-
6.6 Work covered by SWMS is monitored to ensure compliance and adequacy/effectiveness of controls
7. Workplace Inspections
-
7.1 HSEQ inspections conducted at periodic intervals
-
7.2 Subcontractors and management participate in inspections
-
7.3 Records kept and results communicated
-
7.4 Actions developed, implemented and closed out
8. Hazard Reporting
-
8.1
-
8.2 Supervisors action hazard reports
9. Incident Reporting
-
9.1 Requirements communicated and known by all personnel
-
9.2 Incidents (incl. environmental incidents) reported and recorded
-
9.3 Investigations completed where required
-
9.4 Corrective actions addressed and closed out
10. Response and Recovery
-
10.1 Emergency response procedures current and accessible
-
10.2 Emergency equipment, exit signs, paths of travel and alarm systems inspected, tested and maintained at regular intervals
-
10.3 Emergency response procedures have been tested (Drills conducted)
-
10.4 Evacuation maps are prominently displayed and understood
-
10.5 Locations for fire extinguishers identified and marked
-
10.6 Extinguishers of the correct type, inspected, tagged and current
-
10.7 Personnel trained in use of emergency equipment
11. First Aid
-
11.1 First aiders clearly identified
-
11.2 First aid kits provided and contents regularly checked
-
11.3 Register of first aid treatments maintained
-
11.4 First aid facilities are sign posted
-
11.5 Emergency phone numbers, location of doctor/ hospital are displayed
12. Amenities
-
12.1 Amenities and offices adequate for number of employees
-
12.2 Amenities and washing facilities provided kept clean, tidy and hygienic
-
12.3 Amenities and offices have fire extinguishers
-
12.4 All appliances clean, operational and tagged:- air conditioners/ heaters/ urns/hot water units/drinking water/refrigerators-food warmers/microwaves
-
12.5 Adequate noticeboards in place, including HSE noticeboard
-
12.6 Safety signs are in good condition and clearly visible
13. Work Environment and Housekeeping
-
13.1 Good site layout all access/egress ways kept clear, work areas neat and tidy, walking surfaces in good condition and work areas well lit
-
13.2 All stairs and landings are clear from obstructions
-
13.3 Barriers in place around open areas, pits and ramps, railings in place to guard ladder ways and wall openings
-
13.4 Emergency exits clearly signed and unobstructed Clear access to fire extinguishers/hose reels
-
13.5 ‘No Smoking’ and ‘Smoking Permitted’ areas clearly marked
14. Storage
-
14.1 Materials stored off the ground
-
14.2 Storage areas covered and weather proof
-
14.3 Materials protected against damage
-
14.4 Materials easily identified
15. Personal Protective Equipment (PPE)
-
15.1 Correct PPE being worn
-
15.2 Eye protection (double shielding where necessary)
-
15.3 Gloves (Minimum Cut 3 rating)
-
15.4 Safety boots
-
15.5 Safety Hats
-
15.6 Long sleeves and trousers
-
15.7 High visibility vests or shirts
-
15.8 Hearing, Respiratory, Safety harness used where required or specified
16. Work Permits
-
16.1 Necessary work permits obtained/monitored/complied with as required:
-
16.2 General Work Permit
-
16.3 Hot Work
-
16.4 Working at Heights
-
16.5 Live Work
-
16.6 Excavation
17. Hazardous Substances
-
17.1 Assessments completed
-
17.2 Hazardous substances stored/labelled correctly and in secured area
-
17.3 Appropriate PPE being worn correctly, additional PPE available to manage appropriate substances
-
17.4 SDSs and register readily available and current
-
17.5 Warning notices and placards in place
-
17.6 Area free of chemical spills
18. Flammables and Compressed Gases
-
18.1 Flammable substances stored as per regulations and will not contaminate area or equipment (e.g. bunded)
-
18.2 Warning signs visible including No smoking/naked flame signs
-
18.3 Gas cylinders are segregated by type and full/empty
-
18.4 Adequate ventilation
19. Electrical
-
19.1 Electrical equipment in good condition and tagged correctly
-
19.2 Residual Current Devices (RCDs) tested and results recorded
-
19.3 Certificates obtained for RCDs in boards
-
19.4 Earth leakage devices available, in use and tagged
-
19.5 Covers on and locked on distribution boards
-
19.6 Out of service/danger tags used
-
19.7 Cables secured and organised
20. Tools and Equipment
-
20.1 Correct tools being used for tasks
-
20.2 Safe operating procedures available for specific tools
-
20.3 Guarding adequate and correct voltage/air pressure being used
-
20.4 Inspected/serviced regularly
-
20.5 Cables/hoses/connectors/earthing/ check/etc in good condition
-
20.6 Damaged items tagged ‘Out of Service’ and removed from service
-
20.7 Stored correctly
21. Cartridge Operated Tools
-
21.1Trained/licensed operator
-
21.2 Appropriate shielding/containment
-
21.3 Control of cartridges (authorised personnel only)
22. Isolation
-
22.1 System in place to de-energise electrical/pneumatic/hydraulic equipment
-
22.2 Personnel understand/competent in requirements
-
22.3 Use of isolation tags/locks
-
22.4 Faulty construction plant and equipment is tagged out of service/isolated
-
22.5 Faulty plant and equipment is inspected, maintained, repaired and approved by a competent person
23. Working at Heights
-
23.1 Permit obtained where required
-
23.2 Height hazards controlled by permanent or temporary handrails or scaffolding
24. Mobile Elevated Work Platforms (MEWP's)
-
24.1 Plant Operators have a certificate of competency and hold the relevant High Risk Licence (where applicable)
-
24.2 Work covered by a SWMS/permit
-
24.3 Pre-start checks completed / maintenance records current
-
24.4 Controls clearly marked /Marking of Safe Working Load (SWL)
-
24.5 Handrails in good condition and secure
-
24.6 Harness used (where applicable)
25. Scaffolding
-
25.1 Erected correctly by a competent person. For scaffolding over 4m, erection was performed by licensed scaffolders.
-
25.2 Scaff-tag or similar in place
-
25.3 Guard rails, boards, toe boards in place
-
25.4 Scaffold tied to structure
-
25.5 Platforms free from debris
-
25.6 Mobile scaffold is working correctly, on secure level surfaces
26. Ladders
-
26.1 Inspected/serviced regularly
-
26.2 In good working order and damaged ladders removed from service
-
26.3 Wooden or fibreglass for electrical works
-
26.4 Platform Ladders to be used to work from (not A-Frame Ladders)
-
26.5 Extension Ladders being used as access and correctly:
-
26.6 No dangerous situations, correct angle placement and tied off
-
26.7 Three points of contact method used
-
26.8 Ladders extend 1m above level of exit
27. Fall Protection Equipment (Eg Lanyards and Harnesses)
-
27.1 Register available of all fall protection equipment on site
-
27.2 Maintenance and inspection schedule for fall protection equipment
-
27.3 Records of maintenance and inspection kept
-
27.4 Equipment stored correctly
-
27.5 Personnel using fall protection equipment hold a certificate of competency
-
27.6 Fall arrestor anchor points certified, checked and tested
28. Lifting, Rigging, Cranes and Lifting Equipment
-
28.1 Licensed operators
-
28.2 Maintenance log kept (Cranes)
-
28.3 Operational instructions legible/available and permits current
-
28.4 Warning signs notices displayed
-
28.5 Lift studies have been conducted and records kept
-
28.6 Operational areas clear of power lines
-
28.7 Lifting equipment register in place and up to date
-
28.8 Lifting equipment in good condition (no signs of broken wire ropes, severed wires and strands, rust, corrosion, kinks, dog legs, signs of damage or abuse, down grading of slings, etc)
-
28.9 Repairs correct/satisfactory
-
28.10 Records of inspection and maintenance kept for lifting equipment
-
28.11 Lifting equipment correctly stored
-
28.12 Lifting equipment marked - Safe Working Load (SWL)
29. Motor Vehicles / Mobile Plant
-
29.1 Plant Operators have a certificate of competency and hold the relevant High Risk Licence (where applicable).
-
29.2 Pre-start checks completed and recorded
-
29.3 Maintenance log kept
-
29.4 Seatbelts fitted and used
-
29.5 Fire extinguisher installed
-
29.6 Reversing alarms, flashing lights
-
29.7 Loads appropriately secured
30. Welding and Cutting
-
30.1 Hot work Permit and Extinguisher in place
-
30.2 Goggles, gloves, helmets etc suitable for job
-
30.3 Screens shields and warning signs in place
-
30.4 All equipment, leads, connectors in good condition and grounded correctly
-
30.5 Cutting torches in good condition
-
30.6 Cylinders secured/upright
-
30.7 Hose and regulators in good condition and protected against fire/physical damage, flashback arrestors fitted
31. Excavations
-
31.1 Underground services identified/protected
-
31.2 Adequate access/egress
-
31.3 Barriers/warnings in place
-
31.4 Shoring/sloping/stepping adequate for conditions
-
31.5 Rebar ends protected
-
31.6 Spoil clearance and plant/equipment clearance adequate
32. Confined Spaces
-
32.1 Risk Assessed and entry procedure documented, area sign posted and access restricted
-
32.2 Personnel trained and stand-by person available
-
32.3 Emergency procedure in place, approved and consulted
-
32.4 Ventilation adequate and low voltage lighting used
-
32.5 Atmospheric testing conducted, Test equipment (eg atmospheric monitor) calibration up to date and records available
33. Hot Work
-
33.1 Risks identified and Permits issued
-
33.2 Fire protection available
-
33.3 Stand-by person appointed, if applicable
34. Hazardous Manual Tasks / Ergonomics / Repetitive Work
-
34.1 Risk assessments conducted and documented
-
34.2 Personnel trained in safe manual task work practices
-
34.3 Materials have “lift points” where they cannot be easily handled
-
34.4 Suitably rated trolleys and lifting equipment is available and readily accessible to cart and materials
-
34.5 Workstations adjustable to meet requirements of user
-
34.6 Work postures meet ergonomic requirements, are practical for task are adequately addressed
-
34.7 Work processes are set up to reduce twisting and bending
-
34.8 Processes and work areas in place to reduce repetitive work
35. Inspection, Measuring and Test Equipment
-
35.1 Inspection, measuring and test equipment identified, calibrated and logged in register
-
35.2 A schedule of testing dates is available
-
35.3 Inspection, measuring and test equipment maintained & stored correctly
36. Remote Areas
-
36.1 Remote workers have communications which have been tested
-
36.2 Emergency response procedures in place
37. Noise and Vibration
-
37.1 Areas emitting noise/vibration are identified with hearing protection requirements clearly signed
-
37.2 Personnel wearing correct hearing protection
-
37.3 Adequate arrangements to minimise noise pollution
-
37.4 Monitoring where appropriate
-
37.5 Noisy works are carried out during specified hours
38. Spills/Contamination
-
38.1 Environmental response procedures available where required (e.g. chemical spill)
-
38.2 Response and clean up arrangements in place with spill response kits available, stocked, identified and accessible
-
38.3 Personnel trained in environmental emergency response
39. Waste
-
39.1 Waste management systems in place (prevent/reduce/reuse/recycle)
-
39.2 Appropriate segregation of waste
-
39.3 Adequate bins provided
-
39.4 Waste disposal records maintained
40. Water Courses
-
40.1 Appropriate pumping out of excavations
-
40.2 Tanks adequately bunded and bunds intact
-
40.3 Stockpiled materials have sediment controls around them
-
40.4 Stormwater drain sediment controls are in place and effective
41. Air Quality
-
41.1 No black smoke from plant
-
41.2 Dust generation minimised
-
41.3 Mobile Plant is restricted to designated routes to minimise dust
42. Local Community/Surroundings
-
42.1 Impact of traffic minimised
-
42.2 Traffic Management Plan in place where required
43. Flora and Fauna
-
43.1 Endangered flora and fauna have been identified and protected where necessary
-
43.2 Weeds are controlled
44. Quality
-
44.1 Drawings are registered on the drawing register
-
44.2 Drawings or part of drawings being photocopied show drawing number to cross-reference if title block in not part of photocopy
-
44.3 Drawings that are for reference only i.e. architectural, stamped “For Reference Only” on the drawing holder
-
44.4 PC/Laptop used on site, regularly backed-up
-
44.5 ITP’s and ITC’s are initiated as required by the specification or client requirements
-
44.6 ITP’s/ ITC’s are used to verify actual work carried out in the field
45. (Site/Project Specific Inspection Items)
-
45.1
-
45.2
-
45.3