Title Page

MIF.01 - 1ST FIX SVP/ RWP INSPECTION

  • Client: Ballymore

  • Project: Royal Wharf

  • SVP / RWP

  • Apartment Number

  • Block

  • Flat Type

  • Select date

  • Floor

  • Drawing Number

  • Checked by

  • Date:

  • Select date

  • Pipe work and fitting material of construction are subject to correct specification.

  • Preliminary line check as Schematic Piping Specification (Brackets, Vents & Drains).

  • Electro-fusion couplings fused correctly.

  • Pipe work brackets are to correct spacing and installed correctly.

  • Installation and position of expansion joints are correct.

  • Insertion Depth of Expansion Joints as per Depth Gauge on fitting

  • Installation and Position of Access Hatch

  • Access Hatch Height 1200mm from Finished Floor Level

  • W/C pan Connection Height 165mm (±) 5mm

  • No open end unused spigots.

  • System cleared for insulating

  • Snag List

  • Ballymore Supervisor

  • Cilantro Supervisor

  • Select date

  • QC Passed:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.