Information
-
Client / Site
-
Project Job no.
-
Site address
-
Operations Manager
-
Project Manager
-
Quantity Surveyor
-
H&S
-
Site Manager
-
Start on site date
-
Handover date
-
Project duration (weeks)
Part A - 1st fix status queries
-
Are CCTV and Security Contractors required?
-
Is electrical containment in place?
-
When will this be completed?
-
Need to know where the kit is being located? (i.e. in a rack)
-
Have drawings been issued to electrical contractor for containment
-
When will this be completed?
-
Access hatches required?
-
How many do you require and locations?
-
Walk-in Fridge / Catering required?
-
Have power requirements issued to electrical contractor?
-
When will they be?
-
Condenser locations agreed?
-
When will they be agreed?
-
Openings/Walls in place ready
-
By when?
-
Is floor finish in place? (if required prior)
-
When will this be in place?
-
Ready for fridge contractor site attendance to measure?
-
When will this be ready?
-
Any access hatches required?
-
How many and sizes / locations?
-
Shop Front install?
-
Are stall risers complete ready for shop front contractor to attend to take manufacture dimensions?
-
When will they be ready?
-
Signage and Artwork install
-
Position and quantity of access hatches been agreed with Thompsons?
-
What is required?
-
Power requirements agreed with electrical contractor?
-
When can they be supplied?
-
Is power in place ready?
-
When will this be done?
-
Is external fascia ready for signage to be installed?
-
When will this be completed?
-
Is any wall signage/artwork locations been agreed with design team and electrical contractors?
-
When will this be agreed?
-
Is all artwork been checked that is being provided to ensure correct to latest drawings?
-
When can this be checked?
-
Is any other works proposed in areas that may cause delay to signage install?
-
What items
-
BT Openreach / WIFI required?
-
Is comms room/cabinet ready
-
When will it be ready?
-
Is power requirements to cab in place?
-
When will this be ready?
-
Mechanical
-
Are all knock off positions agreed?
-
When will they be agreed?
-
Control panel / fan control positions agreed?
-
When will this be agreed?
-
Canopy requirements / duct clean positions agreed?
-
When will they be agreed?
-
Have all BWIC items been discussed with Thompsons - incl. core holes and fire stopping
-
When can information be supplied?
-
Access hatch quantity/size and locations all confirmed
-
What is required?
-
Electrical
-
Is there an electrical supply present that is suitable for proposed use?
-
What is required?
-
Has a site survey been carried out?
-
When will this be done?
-
Has clash management of containment and ductwork been carried out with mechanical contractors
-
When can this be done?
-
Has all lighting been ordered?
-
When will this be ordered?
-
Will this be on site as programme?
-
When will this land?
-
Will this be on site as programme?
-
Have catering drawings / loading schedule been supplied?
-
When will this be supplied?