Information
-
Client / Site
-
Project Job no.
-
Site address
-
Operations Manager
-
Project Manager
-
Quantity Surveyor
-
H&S
-
Site Manager
-
Start on site date
-
Handover date
-
Project duration (weeks)
Milestone 7 - Construction Phase
-
Project Pack collated - incl. labour model, Programme, material take off, procurement schedule, RFI schedule, Handover checklist as a minimum - Project Manager
-
When will this be completed?
-
What is the programme percentage (%)
-
Any issues to programme - if so; what issues?
-
Carried out delay photo record and site measures - Project Manager
-
When going to undertake?
-
Is welfare in place on site?
-
When will it be done?
-
Is actual labour model up to date? - Project Manager
-
When will it be done?
-
Have all materials been ordered? - Buyers
-
What is remaining to order?
-
Is CVR updated? - Quantity Surveyor
-
When will this be done by?
-
What margin are we looking at currently?
-
Is procurement Schedule up to date? - Quantity Surveyor
-
What is outstanding?
-
When will orders be placed?
-
Have all Have all subcontractors been contacted on the back of QS orders and agreed to proposed programme dates? - Project Manager
-
When will they be contacted?
-
Any that have been do they have all the information they need to carry out work?
-
Who needs information?
-
What information do they need?
-
When will they receive this?
-
Have all variations been supplied to QS to date - Project Manager
-
When will they recieve?
-
Have all variations been costed and financial statement supplied to PQS?
-
When will they be sent?
-
Has the client approved to proceed?
-
Have any amended drawings been distributed from designers? - QS / PM
-
What drawings?
-
Have all changes been captured commercially?
-
When will they be reviewed and cost sent to client?
-
Have all changes been captured operationally - I.e. materials ordered, labour procured etc..
-
When will the materials/labour be sorted?
-
Has a H&S audit been undertaken? - Project Manager
-
Have any/all issues been addressed?
-
When will this be completed by?
-
What was the received score?
-
Is weekly progress reports being sent to client and directs? - Project Manager
-
Why not?
-
Quality checks being undertaken on works throughout and before subcontractors leave for there completed works - Site Manager
-
Why not?
-
Has CCTV drain survey been carried out and report supplied to client? - Project manager
-
When is this being undertaken?
-
Any remedial actions required?
-
Is site paperwork up to date? - Project Manager
-
When will this be sorted out
-
Any issues with neighbouring properties? - Project Manager
-
What are the issues
-
What is done to rectify?
-
Has handover schedule request been sent to H&S team? - Project Manager
-
When will this be sent?
-
When will this be ready - H&S
-
Have all certificates been received for the file?
-
Who is outstanding
-
Where plumbing is to be undertaken in house - has a plumbing statement been done? - Project Manager
-
When will this be done?
-
Has a pre-snag list been compiled on the scheme prior to client snagging?
-
When is this organised for?
-
Have all direct contractors been engaged to confirm attendance for directs week?
-
When will this be actioned?