Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
REQUIREMENTS
-
Is there any delivery instructions or a specific delivery window
-
Site access adequate for a semi trailer
-
Is there a designated loading zone
-
Is the loading zone clearly labelled, including DG and safety signage
-
Are the chlorine drums/cylinders stored on a sealed surface
-
Are the chlorine drums/cylinders stored in a secure area
-
Does the site have lifting equipment to unload drums and cylinders in crates
-
If there is no site lifting equipment is there enough room for the forklift to manouver safely
-
Is there any emergency equipment available to contain an accidental release of chlorine gas on site
-
Does the driver need to complete a site specific induction
-
Is the driver made aware of the site evacuation plan and muster points on each visit
-
INSPECTED BY