Welcome

Underground Conduit Installation

  • Project- Kawana Shopping Centre

  • Project # 1900

  • Client-Mirvac

  • ITP Number

  • Discipline

  • Drawing reference

  • Date ITP commenced

ITP

Underground conduit installation

  • Location and Description

  • Check for latest drawings and co-ordinates

  • Compliance Criteria - Drawings Civil and electrical

  • Drawing number and rev

  • Hold point- No

  • Method of inspection- Visual, Administrate

  • Person responsible- Supervisor or Foreman

  • Name

  • Date

  • Excavate to required depth in accordance with relevant trench cross section

  • Compliance Criteria - Drawings Trench cross section, HV Longitudinal section, Datum Point
    Hold point- No
    Method of inspection- Visual, Measurement

  • Person responsible- Foreman or Leading Hand

  • Install conduits low level

  • Compliance Criteria - Drawings and Electrical Specification

  • Hold point- Yes

  • Method of inspection- Visual or Photographic

  • Photos as required

  • Photo
  • Photo

  • Person responsible- Leading Hand

  • Name

  • Date

  • Back fill trench low level

  • Compliance Criteria - Electrical Specification

  • Hold point- No

  • Method of inspection- Visual or Measurement

  • Person responsible- Leading Hand

  • Name

  • Date

  • Install Electrical or Communications marker tape at correct height. Back fill with required back fill to designated height- IF LEAN MIX USED SEPARATE ITP REQUIRED

  • Compliance Criteria - Electrical Specification

  • Hold point- No

  • Method of inspection- Visual or Measurement

  • Person responsible- Leading Hand

  • Name

  • Date

  • Compact Trench

  • Compliance Criteria - Electrical Specification

  • Hold point- No

  • Method of inspection- Visual or Test

  • Person responsible- Leading Hand

  • Name

  • Date

  • Submit to MIRVAC- ITP, Relevant Mark Up drawing indicating area trenched and compaction test

  • Compliance Criteria - Electrical Specification

  • Hold point- No

  • Method of inspection- Visual or Test

  • Person responsible- Leading Hand

  • As-built drawing

  • Compaction test

  • Name

  • Date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.