Underground Conduit Installation
-
Project- Kawana Shopping Centre
-
Project # 1900
-
Client-Mirvac
-
ITP Number
-
Discipline
-
Drawing reference
-
Date ITP commenced
ITP
Underground conduit installation
-
Location and Description
-
Check for latest drawings and co-ordinates
-
Compliance Criteria - Drawings Civil and electrical
-
Drawing number and rev
-
Hold point- No
-
Method of inspection- Visual, Administrate
-
Person responsible- Supervisor or Foreman
-
Name
-
Date
-
Excavate to required depth in accordance with relevant trench cross section
-
Compliance Criteria - Drawings Trench cross section, HV Longitudinal section, Datum Point
Hold point- No
Method of inspection- Visual, Measurement -
Person responsible- Foreman or Leading Hand
-
Install conduits low level
-
Compliance Criteria - Drawings and Electrical Specification
-
Hold point- Yes
-
Method of inspection- Visual or Photographic
-
Photos as required
Photo
-
Photo
-
Person responsible- Leading Hand
-
Name
-
Date
-
Back fill trench low level
-
Compliance Criteria - Electrical Specification
-
Hold point- No
-
Method of inspection- Visual or Measurement
-
Person responsible- Leading Hand
-
Name
-
Date
-
Install Electrical or Communications marker tape at correct height. Back fill with required back fill to designated height- IF LEAN MIX USED SEPARATE ITP REQUIRED
-
Compliance Criteria - Electrical Specification
-
Hold point- No
-
Method of inspection- Visual or Measurement
-
Person responsible- Leading Hand
-
Name
-
Date
-
Compact Trench
-
Compliance Criteria - Electrical Specification
-
Hold point- No
-
Method of inspection- Visual or Test
-
Person responsible- Leading Hand
-
Name
-
Date
-
Submit to MIRVAC- ITP, Relevant Mark Up drawing indicating area trenched and compaction test
-
Compliance Criteria - Electrical Specification
-
Hold point- No
-
Method of inspection- Visual or Test
-
Person responsible- Leading Hand
-
As-built drawing
-
Compaction test
-
Name
-
Date