Title Page
-
Site Address
-
Conducted on
-
Conducted by
-
Trades Present
Site General
-
Does the site appear in a generally acceptable condition (eg clear of uncontained rubbish / materials, clear access ways etc) ?
-
Is there a perimeter fence in place to deter unauthorised access ?
-
Is there site signage in place as required by legislation ?
-
Is there reasonable access to power, potable water and toilet facilities ?
-
Is there reasonable access to rubbish collection / disposal facility (eg cage / skip bin etc, being serviced as needed) ?
-
Have Trades complied with their "Housekeeping" obligations ? (Excess materials and rubbish removed, clear access ways etc)
Administration
-
Is there a Site Specific safety plan available ?
-
Have workers completed a Site Specific Induction (where required) and have GSI cards available for inspection ?
-
Is there a recent (within the last 12 months) SWMS for designated High Risk Construction Work, read, understood by all workers involved and complied with ?
-
Are SDS's readily available and understood, for any Hazardous Materials in use ?
-
Is there access to First Aid supplies and advice, suitable for the work being done and number of workers involved ?
-
Do workers appear to working in a safe manner ? Were tool box talks conducted ?
Personal Protective Equipment
-
Are workers using appropriate PPE for the risk(s) / work being done ?
-
Are workers wearing Hard Hats where there is a risk of being hit by falling materials / tools (eg under concrete booms) ?
-
Are workers wearing HiVis clothing (if required) and suitable foot ware ?
Excavations
-
Have excavations deeper than 1.5m been benched, battered or shored (barricaded / covered if left unattended) ?
-
Have pier holes, pits, steep and deep batters etc been barricaded if left unattended ?
-
Have vertical reinforcing rods, star pickets etc been protected (plastic caps or similar) ?
Working at height
-
Has a SWMS for work above 2m been prepared within the last 12 months, signed and understood by all workers and a copy been provided to the Principal Contractor ?
-
Is the SWMS readily available and being complied with ?
-
Are access ladders set up correctly (1:4 / clamped / extended 1m above landing etc) ?
-
Are voids and stairwells protected (eg proprietary void platforms / handrails etc) ?
-
Is roof edge protection in place where required and continuous ?
Scaffold
-
For scaffold 4m and above, is there a current "Handover Certificate" signed and dated within the last 30 days ?
-
Does the scaffold appear complete and unaltered ?
-
Are baseboards in place and suitable (set-up and material) - mobile scaffold wheels secure and chocked ?
-
Have toe boards been installed (especially scaffolds over 4m high) ?
Ladders
-
Do ladders appear to be in a good, undamaged condition ?
-
Are ladders set up correctly (1:4 / secured from slipping etc) and Industrial / Commercial, with a minimum 120kg load rating ?
-
Are ladders suitable for specialist applications (eg Fibreglass / wood for live electrical work ?
Mobile Plant
-
Does mobile plant appear to be in good, serviceable condition ?
-
Is the plant registered (where required by Law) and have relevant maintenance / test records available ?
-
Is the Operator Licenced (where required by Law) and observed as being competent in the use and operation of the plant ?
-
Is a Mobile a Plant SWMS readily available, understood and being followed by involved workers ?
-
Are plant alarms fitted and operational (reversing beeper / flashing beacon etc) ?
Electrical
-
Do Trade's electrical tools and equipment appear to be in a safe, undamaged condition ?
-
Are Trades electrical tools and equipment tested and tagged at 3 month intervals (current tags / records) ?<br><br>
-
Is the electrical supply (eg Domestic Meter Box) AS3012 compliant ?
-
Is the Construction Power circuit RCD tested regularly (PC monthly, Trades daily) ?
-
Are Trade's electrical leads a suitable length and run to avoid standing water and mechanical damage ?
-
Have overhead powerlines been identified, risk assessed and protected where there is a possible risk to plant and workers ?
Environmental
-
Have environmental protection measures been implemented (eg sediment controls, temp downpipes, mulch, settlement ponds etc) ?
-
Are hours of operation restrictions / noise reduction / dust suppression measures in place ?