Information
-
Project Name
-
Contract No:
-
Document No.
-
Conducted on
-
Location
-
Contractor:
-
Prepared by:
- Jason Clements (MLEI)
- James O'Conner (MLEI)
- Adam Grant (MCC)
- Brendan Howard (MCC)
- Alan Michie (FBE)
- Steve Morton (RGS)
- Other
Your Own Safety
-
Have you read and are you able to comply with your Site Visit SWMS?
-
Do you know what PPE you need? and do you have it available for your visit?
-
Did you participate in a relevant Site Induction and Pre Work Brief (PWB) when you reached the Contractor's site?
-
Do you have the local site contract persons contact details? Have they been informed?
Site Safety
All Work Places including Offices
-
Contractor's WHS officer onsite
-
Knowledge of & access to WHSMP
-
Evidence of contractors undertaking WHS checklists and actions closed
-
Fire Equipment available, signposted, good condition, tagged
-
Emergency Egress clear
-
Wardens appointed/ signposted
-
Evidence of positive identification of services including overhead wiring.
-
Electrical leads checked/tagged (every 3 months on construction sites)
-
Adequate empty bins / skips and separation of waste types
-
Lighting adequate
-
Amenities clean and hygienic (Toilets, lunchrooms etc)
-
Hazardous substance register and MSDSs
-
Safe Stacking and Storage
-
Walkways, floors and aisles clear
-
General housekeeping and cleanliness
-
First Aid facilities available & First Aid officer signposted
-
If Manual handling - SWMS available and followed
-
Fencing & Security adequate, good condition.
-
Community contact/ helpline available
Additional Checklist for Construction Sites
-
Pre Work Brief recorded and signed by all workers.
-
Construction work SWMS available, signed and being followed.
-
Slips, trips and falls managed, trenches and holes covered or barricaded.
-
PPE requirements signposted, and PPE compliance
-
Are the site access and exit points clear and safe
-
Adequate separation of traffic and workers
-
Plant movement on site safe and controlled with separation of LV and HV
-
Work Permits in use for Construction, Hotwork, Excavation, Work at Height.
-
Plant operations. Licenses. Pre use checks recorded. Condition of plant.
-
Lifting equipment. Up to date Tagging; in good condition.
-
Parking is marked and orderly and not spilling onto road network. Separation for pedestrians.
-
Work at Height SWMS, PPE harness appropriately attached.
-
Traffic Management Plan in place and working.
Signoff
-
Signoff