Information

Details of repair

  • Property address

  • Client Reference

General Description

  • Erected by

  • Mobile/Static

  • Double/Single

  • Type

  • Tower Manufacturer

  • Height in meters

  • Date/time erected or last modified

  • Location of tower at inspection

  • Photo of location, if necessary

  • Completed by

  • Conducted on

  • Your location can be autofilled here (for speed, good signal required) this will not be as accurate as manually completing the address

Inspection detals

The Timing of Inspections

  • This checklist refers to one of the following timings (please tick as appropriate)

  • After any substantial addition, dismantling or other alteration

  • After any event likely to have effected its strength and/or stability

  • At regular intervals NOT exceeding 7 days

  • The following must be checked

  • Do you have a copy of the manufacturers instruction manual to enable you to check the tower?

  • Does a risk assessment to the tower exist?

  • Check that the environment has no detrimental affect on the safe use of the tower

  • Are the castors or base plates in contact with the ground and bearing their share of the weight of the tower and that all four breaks are applied?

  • Are the adjustable legs only being used to level the tower and not for gaining height?

  • Is the tower level in all planes?

  • Is the tower built on firm and stable ground?

  • Are stabilisers fitted and are they the correct size for the height of the tower?

  • Check that the feet are fully in contact with the ground, and wing nuts are tight?

  • Check that the foot of the stabilisers are positioned to form a square?

  • Is the bracing pattern used, in accordance with the manufactures instructions?

  • Check that the hooks on the braces are fully engaged?

  • Check that all the handrails and mid guards are fitted in the correct positions?

  • Check that the interlocking device, locking frames together are engaged?

  • Check that all platforms are in the correct position on the tower?

  • Check that the trap door opens to the outboard side of the tower?

  • Is the working platform at least 600mm wide?

  • Check that, if the tower is single width, that all platforms have trap doors?

  • If wind locks are fitted to the platform, check that they are engaged?

  • Are toe boards fitted to the working platform, or any platform with gear stowed?

  • Are you are aware of the maximum permitted load on the platform/structure?

  • Is the Mobile Tower Scaffold to be erected at least four meters away from any overhead power lines?

  • If necessary, has the work area been cordoned off?

  • If the tower is to be left incomplete has a sign been attached that warns it’s unsafe?

Sign Off

Inspection Completed - Sign off

  • I have inspected the tower, which is identified by the reference number below

  • Tower Tag reference number

  • Name / signature of inspector

  • Photo of Tower Tag

  • Link to HSE website for Towers
    http://www.hse.gov.uk/construction/safetytopics/scaffold.htm

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.