Information
-
ITP N248-006-
-
Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
Pre-Pour Inspection
-
Position of the plinths is correct
-
Reinforcement has been drilled, epoxied and tied correctly
-
Correct concrete cover for reinforcement is achieved (45mm top cover)
-
Formwork has been secured sufficiently
-
Correct concrete placement level has been identified on Formwork
-
Pour area is clean and free from foreign material
-
Lend Lease Client approved the pour?
-
Approved For Pour (KNF supervisor to sign)
Post - Pour Inspection
-
Concrete placed and compacted correctly
-
Finish levels and locations correct
-
All Formwork stripped and bundled correctly
-
Finished product free from NCRs (if no please provide detail of NCR and fill in NCR form)
-
Finish Product Approved