Pre-Pour Inspection

  • Position of the plinths is correct

  • Reinforcement has been drilled, epoxied and tied correctly

  • Correct concrete cover for reinforcement is achieved (45mm top cover)

  • Formwork has been secured sufficiently

  • Correct concrete placement level has been identified on Formwork

  • Pour area is clean and free from foreign material

  • Lend Lease Client approved the pour?

  • Approved For Pour (KNF supervisor to sign)

Post - Pour Inspection

  • Concrete placed and compacted correctly

  • Finish levels and locations correct

  • All Formwork stripped and bundled correctly

  • Finished product free from NCRs (if no please provide detail of NCR and fill in NCR form)

  • Finish Product Approved

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.