1.0 - Work Specification & Result Sheet No. Including issue date.
-
Section, Document numbers and issue dates:
-
1.1 - Do the document numbers & issue numbers match the latest version on Sharepoint?
-
Any comments:
-
1.2 - Have the Work Order Numbers been pre-printed on the Record Sheet and issued to the current job?
-
Any comments:
-
1.3 - Confirm that the record sheet and the corresponding piece of equipment have both been annotated with the Unique number.
-
Any comments:
-
1.4 - Check all calibrated tools are in date, torque wrenches have been checked daily and recorded on the torque tester?
-
Any comments:
-
1.5 - Check to see there has not been any unauthorised alterations to the document?
-
Any comments:
-
1.6 - Is the Result Sheet being completed concurrently as each task is being completed?
-
Any comments:
-
1.7 - check all consumables are correct for the work being carried out and in date?
-
Any comments:
-
1.8 - Check that all grey spares are segregated and colour coded iaw the SOP?
-
Any comments:
-
Any comments:
1.1.1 - Work Specification & Result Sheet No. Including issue date.
-
Section, Document numbers and issue dates:
-
1.1.2 - Do the document numbers & issue numbers match the latest version on Sharepoint?
-
Any comments:
-
1.1.3 - Have the Work Order Numbers been pre-printed on the Record Sheet and issued to the current job?
-
Any comments:
-
1.1.4 - Confirm that the record sheet and the corresponding piece of equipment have both been annotated with the Unique number.
-
Any comments:
-
1.1.5 - Check all calibrated tools are in date, torque wrenches have been checked daily and recorded on the torque tester?
-
Any comments:
-
1.1.6 - Check to see there has not been any unauthorised alterations to the document?
-
Any comments:
-
1.1.7 - Is the Result Sheet being completed concurrently as each task is being completed?
-
Any comments:
-
1.1.8 - check all consumables are correct for the work being carried out and in date?
-
Any comments:
-
1.1.9 - Check that all grey spares are segregated and colour coded iaw the SOP?
-
Any comments:
1.2.1 - Work Specification & Result Sheet No. Including issue date.
-
Section, Document numbers and issue dates:
-
1.2.2 - Do the document numbers & issue numbers match the latest version on Sharepoint?
-
Any comments:
-
1.2.3 - Have the Work Order Numbers been pre-printed on the Record Sheet and issued to the current job?
-
Any comments:
-
1.2.4 - Confirm that the record sheet and the corresponding piece of equipment have both been annotated with the Unique number.
-
Any comments:
-
1.2.5 - Check all calibrated tools are in date, torque wrenches have been checked daily and recorded on the torque tester?
-
Any comments:
-
1.2.6 - Check to see if there has not been any unauthorised alterations to the document?
-
Any comments:
-
1.2.7 - Is the Result Sheet being completed concurrently as each task is being completed?
-
Any comments:
-
1.2.8 - check all consumables are correct for the work being carried out and in date?
-
Any comments:
-
1.2.9 - Check that all grey spares are segregated and colour coded iaw the SOP?
-
Any comments:
Section 2 - Risk Assessments and Method Statements (RAMS)
-
Ensure the the RAMS match the work activities audited in section 1. Record the RAMS number and issue date.
-
Are the RAMS clearly displayed, either on the section HUB or at the place of work?
-
Comment section:
-
Are the RAMS the latest version?
-
Comment section:
-
Is the PIC of the work activity on site?
-
Comment section:
-
Have the RAMS been signed onto by all on the working party register?
-
Comment section:
Section 2.1 - Risk Assessments and Method Statements (RAMS)
-
Ensure the the RAMS match the work activities audited in section 1. Record the RAMS number and issue date.
-
Are the RAMS clearly displayed, either on the section HUB or at the place of work?
-
Comment section:
-
Are the RAMS the latest version?
-
Comment section:
-
Is the PIC of the work activity on site?
-
Comment section:
-
Have the RAMS been signed onto by all on the working party register?
-
Comment section:
Section 2.2 - Risk Assessments and Method Statements (RAMS)
-
Ensure the the RAMS match the work activities audited in section 1. Record the RAMS number and issue date.
-
Are the RAMS clearly displayed, either on the section HUB or at the place of work?
-
Comment section:
-
Are the RAMS the latest version?
-
Comment section:
-
Is the PIC of the work activity on site?
-
Comment section:
-
Have the RAMS been signed onto by all on the working party register?
-
Comment section:
Finish