Information
-
Customer
-
Store Number & Name
-
Conducted on
-
Location
-
Senior Install Engineer
-
Install Engineers
-
Training Shift
-
Trainee Engineers
-
Document No.
-
Proceed to next section >
Site Start
-
All NCR engineers signed into Store Visitor log and equipped with appropriate PPE
-
Store Plans/Drawings/Scope Of Work checked
-
Store Number & IP info checked
-
Store IP
-
Reason for Not Applicable/Not Available
-
Delivery Checked
-
Delivery checked at
-
All kit delivered as expected
-
Click "Add Part" to record each instance of missing kit/parts
Part
-
Part Description
-
Issue escalated to
-
Date/Time of escalation
-
Reason for delivery not checked/not applicable
-
Proceed to next section >
Work Details
-
Click "ADD DEVICE/ITEM" to record details of each device/item of work being carried out as required.
*Please check job requirements for serial number capture - if in doubt, capture it*
DEVICE/ITEM
Scope Of EPOS/IMAC Work
-
Description/scope of work carried out on Device/Item
-
Area of Works/Location of Device/Item
Device/Item Details
-
Device Serial Number (if required)
-
Device Model/PID (if required)
-
Display Serial Number (if required)
-
Receipt Printer Model/PID (if required)
-
Receipt Printer Serial (if required)
-
Scanner Scale Model/PID (if required)
-
Scanner Scale Serial Number (if required)
-
Hand Scanner Serial Number
-
PED Model (if required)
-
PED Serial
-
Catalina Serial Number (if required)
-
Catalina MAC Address (if required)
Network Details
-
Device IP Address (if required)
-
Gateway IP Address (if required)
Completion
-
Work Successfully Completed
-
Image of work completed
-
Reason for Work Not Successfully Completed
-
Comments
-
Click "ADD DEVICE/ITEM" to record details of each device/item of work being carried out as required.
*Please check job requirements for serial number capture - if in doubt, capture it* -
All work details checked and recorded correctly?
Site Sign Off
Senior Engineer Sign Off
-
Date/Time of Completion
-
By ticking the box, the Senior Install Engineer is confirming that all work and tests were completed as per NCR and Customer Requirements
-
Area of work upon completion
Customer Sign Off
-
Please enter any additional comments or notes here
-
The installation was successfully completed and all items either work properly or have an acceptable plan to rectify any issues satisfactorily
-
Store Representative Position
-
Store Representative Name & Signature
-
Miscellaneous