Title Page

  • Project Name

  • Scheme No

  • Conducted on

  • Prepared by National Grid Supervisor

  • Location
  • Principal Contractor

  • Programme Week No

  • Weather conditions

  • Work Location - As per 4 week look ahead

  • Work Item - As per 4 week look ahead / Daily Activity Boards

Sub Contractors on site

  • List Sub Contractors and how many members of staff working

  • Equipment On Site
  • Type

  • How Many Units on site

Project Progress

  • Progress updates: eg started on time, on track to finish on time, finished late and or %age complete based on 4 week ahead programme

  • On Track

  • Comments

  • Comments to PE

Significant stakeholder discussions (e.g. ETO / UKPN / Babcock)

  • Type Answer

"Materials / Deliveries to Site, (including quantities and what aspect of work required for)"

  • undefined

Early Warning Events/ Flags to PEs:

  • Type Answer

  • Daily Work Log
  • Work commenced - all notes to be added

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.