Title Page
-
Contract number
-
LA Code
-
Location
-
Prepared by
-
Date of Inspection
-
Team Supervisor
-
Additional personnel on site
-
Brief description of work activity
-
Client
-
Principle Contractor
Health and Safety
-
Daily Risk Assessment / JSSP available and signed off by relevant staff?
-
All site operatives signed on / off site?
-
All site operatives inducted?
-
Staff appropriately trained for the works being carried out?
-
Method Statements and Risk Assessment available and signed by relevant staff?
-
NI10 form available?
-
Permit to Work in place?
-
Correct PPE being worn? (Behaviour / Compliance)
-
Seat belts being worn when operating plant?
-
Suitable site access and egress?
-
Signing / Lighting / Guarding in place where applicable?
-
Stop / Go boards available as backup?
-
Site security adequate?
-
Housekeeping adequate? (Slips / Trips / Falls)
-
Work on or near water properly planned?
-
Lift plan / Appointed Person in place?
-
Working at Height properly planned?
-
Scaffolding fit for purpose and appropriate inspections carried out?
-
Aluminium tower fit for purpose and appropriate inspections carried out?
-
Measures in place to safely manage and control Temporary Works?
-
Excavations safely guarded / battered back?
-
Weekly inspection of excavations completed?
-
Asbestos Refurbishment & Demolition Survey Report / Register available?
-
Tool Box Talks being carried out weekly?
-
Good catches being recorded?
Kit & Equipment
-
Weekly LOLER / PUWER inspections completed?
-
Thorough examination certs available for all plant and equipment?
-
Thorough examination certs available for all lifting equipment?
-
Daily plant inspections completed?
-
Daily HGV inspections completed?
-
Wheel nut markers in place?
-
CAT & Genny available and calibrated?
-
Fire Fighting Equipment available?
-
First aid kit & eye wash station available?
-
Trained First Aider on site and known to workers?
-
Welfare facilities in place / adequate?
-
Portable Appliance Testing (PAT) in place and up to date?
-
Any hazards that require immediate intervention not listed above?
-
Please state below any other observations identified on site:
-
Please state below any other observations identified on site:
-
Please state below any other observations identified on site:
-
Please state below any other observations identified on site:
Environmental
-
Hazardous substances stored correctly? (eg drip trays)
-
Hazardous substances labelled correctly?
-
Spill kits available?
-
Waste disposed of correctly?
-
Dust and noise control adequate?
-
COSHH assessments available?
-
Please state below any other observations identified on site:
-
Please state below any other observations identified on site:
Quality
-
Quality of works to an acceptable standard?
-
Company insurance policy available and in-date?
-
Company policies available?
-
Company forms used in-line with ISO procedures?
-
Sub-contractors on site QP3 approved?
-
Verification sub-contractor has implemented a modern slavery policy and were not - is working under ACPL policy.
-
Please state below any other observations identified on site:
-
Please state below any other observations identified on site:
NIE
-
NIE Notice Board on display?
-
Sandbags in place on signage?
-
Insulated hand tools available?
-
Underground Services marked?
-
Overhead lines protected?
-
Work instruction and service maps available?
-
Relevant DFI Road Works Permit available & in-date for works?
-
NIE LWC available, in date, and held by an Authorised Person?
-
NIE Permit to Work available, in date, and held by an Authorised Person?
-
Field earth equipment serviceable & tagged?
B947 Cable & Reinstatement
-
Are the correct chains and load binders being used to strap down cable drums?
-
Are the loading bays being used correctly and used for loading cable drums?
-
Are all cables being capped correctly?
-
Are cables and materials being recorded correctly?
-
Confirm that those involved in the loading/unloading of cable drums have the correct training?
-
Are there an adequate compartment in the vehicle for the transportation of gas cylinders?
-
Are the gas torches disconnected from the gas tank when in transportation?
-
B947 - Pre & Post-siting Records completed?
-
B947 - Are cabling teams using radios?
-
B947 Cable - Cable swivel in use?
-
B947 Cable - Use of bell mouths & adequate rollers?
-
B947 Cable - Is cable stocking serviceable and in good condition?
-
B947 - Has reinstatement team left the area clean & tidy?
-
B947 - Has edge sealant been used to seal trench?
-
B947 - Has trench clegg been tested with evidence?
-
B947 - Has base course been compacted with vibrating rammer (not vibrating plate)?