Information
-
Contract Name & Number:
-
Conducted on
-
Prepared by
-
Add location
-
Personnel
GENERAL
-
A. Contract Management Plan (CMP) and appendices on site?
-
B. Site Hazard ID completed and all controls in place?
-
C. Daily Pre-Start Tailgate completed and all staff signed on including visitors and sub-Contractors?
-
D. Staff and subbies clearly describe what was discussed at the prestart tailgate briefing
-
E. Notifiable works
-
F. Relevant SWMS / JSA's available on site
-
G. Permits in place and been complied with (Dial B4 U Dig, Close Approach etc)
-
H. Staff and Operators skill and competency appropriate for the tasks
-
I. Operations are 4m clear of overhead lines at all times
-
J. Seatbelts are being used on all plant
-
K. Reverse parking
-
L. First impression and general housekeeping
WORK AREAS
-
A. Housekeeping and site maintenance is such that slips trips and falls is minimised
-
B. Falls from unprotected edges, excavations and holes managed
-
C. Impalement Hazards (Caps on Waratahs and Reinforcing bars)
-
D. Spotters and safety observers clear of hazard zones
-
E.. Sanitary Facilities available (drinking water and toilets etc)
-
F. Material storage including stockpiles
-
G. Low light conditions managed
-
H. General public and motorists protected after hours
EMERGENCY MANAGEMENT, SIGNAGE AND COMMUNICATIONS
-
A. Policies, Procedures, Newsletters, OFI forms, Values, Rules (eg Tikanga Safety Rules) displayed or available
-
B. Communication, radio, cellphone coverage known
-
C. Emergency Evacuation Assembly Points
-
D. Emergency Contacts List
HEALTH AND FIRST AID
-
A. Trained First Aiders
-
B. First Aid Kits available and well stocked
-
C. Sun protection available and used
-
D. Declared health related issues communicated within the team (eg allergies, diabetes etc)
PERSONAL PROTECTIVE EQUIPMENT
-
A. Compliant Hiviz vests and or clothing zipped up and in good condition
-
B. Hard Hats
-
C. Safety Glasses
-
D. Face Shield / Goggles (If Required)
-
E. Respiratory Protection (If Required)
-
F. Hearing Protection (If required)
-
G. Clothing - long sleeves and trousers
-
H. Gloves
-
I. Laced Steel Toe Caps
-
J. Other
MANUAL HANDLING
-
A. Manual handling risks identified and managed
-
B. Mechanical aids used where available
-
C. Workers able to operate in comfort
-
D. Workers are not lifting heavy items frequently
FALL PROTECTION
-
A. Trained Personnel (Competent Person)
-
B. Harnesses correct fit and worn properly
-
C. Suitable Anchor Points used
-
D. Equipment inspected prior to use and within test
-
E. Equipment stored properly (free from damage)
-
F. Emergency Rescue Plan
LADDERS
-
A. Proper type for task
-
B. Rubber feet condition
-
C. Rungs and stiles condition
-
D. Positioned on flat stable foundation and secured at the top
-
E. Extended 1m beyond top edge
-
C. Other
TOOLS AND EQUIPMENT (non electrical)
-
A. General Condition
-
B. Proper type for task
-
C. Other
EXCAVATIONS
-
A. Dial B4 you dig completed when deeper than 300 mm and services marked out
-
B. Shoring (trench shields) in place when deeper than 1.5m and or suitable batter or bench
-
C. Access and Egress
-
D. Soil Condition assessed
-
E. Water Accumulating
-
F. Barricades
-
G. Spoil pile 1m from edge
-
H. Air Monitoriing
-
I. Emergency Rescue Plan
CONFINED SPACE
-
A. Trained Personnel
-
B. Process and Permit in place and followed
-
C. Air Monitoring
-
D. Emergency Rescue Plan
ELECTRICAL
-
A. Condition of tools and equipment
-
B. Extension Cords protected from damage,Tagged and in Test and RCD's used
-
C. Power Tools Tagged and in Test
-
D. Lock Out Tag Out process understood (fixed plant)
FIRE SAFETY
-
A. Hot Work Permit (if required)
-
B. Fire Watch Assigned (Competent Person)
-
C. Fire Extinguisher within test
-
D. Combustibles removed/isolated
-
E. Hot Work Barricade (if required)
RIGGING AND HOISTING
-
A. Tagged, inspected, certified and in good condition
-
B. Suitable for the task (eg able to take the expected load)
-
C. Permit in place (if required)
PLANT AND EQUIPMENT
-
A. Daily Plant Checklists carried out
-
B. Operator qualified, licensed and competent
-
C. Reversing beeper, camera (where fitted), flashing beacon
-
D. Safe working load displayed
-
E. Operator Manual (for specialist plant)
-
F. Guarding adequate and inplace
-
G. Fire extinguisher and first aid kit
TRAFFIC MANAGEMENT
-
A. TMP number and STMS noted on and Daily Pre-Start Sheet
-
B. Approved TMP on site
-
C. Set up correctly according to TMP and is it effective at controlling traffic and pedestrians
-
D. Adequate separation between live traffic and work area
-
E. Regular 2 hourly checks been carried out and signed off on Daily pre-start tailgate
-
F. STMS and TC staff on site and certified trained
HSNO
-
A. Staff trained (eg GrowSafe) for the products being handled and applied
-
B. Restricted application areas and zones are known by applicators
-
C. MSDS available for all chemicals and hazardous products
-
D. Chemicals stored safely on site
-
E. Proper PPE for Handling Chemicals
-
F. Contaminated containers disposed of appropriatly
ENVIRONMENTAL
-
A. Adequate Environmental Management Plan EMP on site
-
B. Relevant resource consent conditions are understood and being complied with
-
C. Heritage and culturally significant sites are clearly demarcated and known to all on site
-
D. Habitats or species of conservation significance are not disturbed
-
E. Vegetation clearance is kept to a minimum
-
F. Dust suppression techniques are adequate and effective
-
G. Approval has been given to discharge to waterways
-
H. Sediment and run off control measures are adequate and effective
-
I. Noise control measures are adequate and effective
-
J. Spill kits appropriate type and size for the volume of products on site
-
K. Chemicals and contaminates are stored safely and MSDS sheets readily available
-
L. Waste and Energy minimisation measures are being followed
-
M. Prescribed waste (asbestos etc) is being removed and disposed of responsibly
COMMENTS AND RECOMMENDATIONS
-
Enter any corrective actions that will be undertaken
SIGN OFF
-
Safety Representitive
-
Site Supervisor