Title Page

  • Location
  • Conducted on

  • Engineers present

PRE-WORK

  • Presentation of engineer

  • Presentation of vehicle

  • Signed in on site (Or agreed booking on procedure - eg COSC)

  • Relevant induction complete & passes possessed

  • Permits to work obtained

  • Staff fit - free from medical issues/medication declared

  • Alcohol/drugs free & not fatigued

  • Engineer pre-work risk assessment carried out

  • Any change to RA/MS recorded & communicated to client

  • All staff briefed & understand roles/responsibilities

  • Site asbestos/hazard register checked

SAFE SYSTEM OF WORK

  • RA/MS read

  • Has a SSOW been followed as per RA/MS

  • Safe work area created using barriers, cones & signage

  • Good housekeeping (Slips, trips and falls)

  • Equipment tested/in date & fit for purpose

  • Equipment set up correctly (Ladders/MEWPS/TOWERS)

EMERGENCIES & CONTINGENCIES

  • Work contingencies & rescue plans in place

  • Site layout & welfare arrangements understood

  • Site contingency & evacuation plans understood

  • First Aid kit available

  • Spill kit available

POST WORK CHECKS

  • Waste disposed of in accordance with site & Optyma rules

  • Work carried out to NSI/Optyma standards

  • System left safe, in full working order & tested

  • Was paperwork completed correctly

  • CORRECTIVE ACTIONS / OBSRVATIONS

  • ACTION PLAN

  • Inspected by

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.