Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
People Present
Is the contracts manager or the construction lead present
-
Is the commercial manager or commercial lead present <br>
-
Is the site manager, senior site manager or PM present
-
Is the QS or senior QS present
-
Optional - is the BUL present
Control documents
-
Is there a written contract review in place
Section 1 - Matters Arising
-
Is the a copy of the last site team meeting notes attached
-
Is the last Client team meting notes attached
-
Section 1 Notes:
Section 2 - Safety
-
Is the last Osborne Safety Advisers inspection attached, marked up with signed off actions and placed on IGO
-
Is there attached a copy of the last site safety check sheet
-
Section 2 Notes :
Section 3 - Programme & Progress
-
Is there a copy of the Contract Programme, marked with percentage completed, drop line and rescheduled
-
Is there a copy of the target programme marked up with percentage complete, a drop line and rescheduled
-
Is there evidence of short term programmes being used
-
Are we behind programme if so is there a recovery plan
-
Section 3 Notes: <br>
Section 4 - Contractual Matters, Site Overheads, CVC
-
Is there an up to date copy of the CVC/ EDF
-
Copy of cash flow forecast
-
An up to date copy of the procurement schedule
-
Is there a up to date copy of the Warrantee tracker
-
Was the last valuation on time <br>
-
Section 4 Notes:
Section 5 - Labour & Plant
-
Section 5 Notes:
Section 6 - Materials
-
Section 6 Notes
Section 7 Sub-contractors
-
An up to date copy of the subcontractor meeting notes
-
Section 7 Notes:
Section 8 - M & E Matters
-
Section 8 Notes:
-
An up to date copy of the STAT,s tracker
-
Is there a commissioning / test and inspection programme in place
Section 9 - site Admin & Control
-
Copy of Up to date RFI,s schedule
-
Copy of up to date information required schedule <br><br>
-
Copy of Up to date CVI,s
-
Section 9 Notes:
Section 10 Design
-
Copy of last Design team meeting notes
-
Is there a planning condition tracker
-
Date of last update Planing Condition Tracker
-
Section 10 Notes:
Section 11 Risk & Opportunities
-
An up to date copy of the Risk & Opportunities register
-
Section 11 Notes:
Section 12 Snagging
-
Is there a snagging schedule
-
Section 12 Notes:
Section 13 - Company Profile
-
Section 13 Notes:
Section 14 - Considerate Constructors / KPI,s
-
Copy of considerate constructors report & score
-
Section 14 Notes
Any Other Business
-
AOB Notes:
Checks
-
Is gateway No 7 complete
-
Undertake review of Gateway 8
-
Was the last Opp,s report completed on time
-
Was the last Opps report filed correctly
-
Is the project score sheet up to date
-
Is the Project PEP up to date
-
Has the latest ICE been reviewed in the last month
-
When was the update of the Site Waste Management Plan
General Site Safety
-
Date of last update of Health & Safety Plan
-
Is the fire risk assessment / fire plan up to date
-
Is the logistics and traffic management plan up date
-
Is the F10 up to date
-
Comments on safety
Resource requirement:
-
Resources required or coming free within the next month including any Holiday cover
-
Resource required or coming free within the next 3 months including holiday cover:
Score & Comments
-
Date of next Contract Review:
-
Date of next 4 Weekly Health & Safety Review
-
Date of Phase One Hand Over
-
Date of next Opps report
-
Date of Phase Two Hand Over
-
Contract Completion Date
-
Projected Completion Date
-
General Comments:
-
Leslie Allen: