Information
-
Conducted on
-
Location
-
Inspection No.
-
Inspection by:
- Greg Douglas
- Chris Gilmore
- Steve Brown
- Warren Hay
-
Project Title
-
Project No.
-
Client / Site
-
Personnel
- Kristian Arnold
- Scott Brodie
- Duncan Brown
- Glenn Brown
- Daniel Cahill
- John Calleja
- Tony Cassanianca
- Drue Eding
- Heath Elton
- Ken Grimmitt
- Glen Mackenzie
- Luke Moir
- Grant Organ
- Tim Palmer
- Paul Vikis
- Lachlan Sampson
- Colin Whitbread
- Ryan Wooden
- Peter Booth
- Colin Carroll
- Warren Hay
- Steve Brown
- Chris Gilmore
- Jamie Moore
- Greg Douglas
-
The field audit is broken into 3 sections, Safety, Environmental and Quality. As a minimum the Safety section should be used.
Note 1: Positive work practices and behaviours should also be recorded.
Note 2: The person issuing the corrective action is responsible for ensuring this form is completed prior to sending to the QHSET manager.
Note 3: return the completed inspection to the QHSET Manager. Zainj@pu.com.au
The following to be completed if the workplace is visited by a Senior Manager.
-
Attended a toolbox talk.
-
Attended a daily pre-start meeting.
-
Task Observation.
-
Training needs identified.
-
Additional comments or observations.
-
Photo record if required.
Safety
Site Personnel.
-
All personnel inducted.
-
Mandatory PPE worn.
-
SMP, SWMS signed and available.
-
HAC completed and site relevant.
-
All people signed onto HAC
-
Access permit on site with all staff signed on.
-
Amenities - toilets, shelter & water available
-
Subcontractor SWMS, HAC and PPE compliant.
-
Spotter available for heavy plant movements and excavations.
-
Competent operators available for plant.
-
Staff appropriately trained and authorised. i.e relevant authority authorisation, licenses, confined spaces etc.
Equipment, Plant & Materials
-
First aid kit, fire extinguisher and low voltage rescue kit available.
-
Perimeter fencing appropriate.
-
Correct fittings used.
-
Flashing lights, motion alarms/reversing beepers operational.
-
Fall protection in place.
-
Handrails and toe boards in place.
-
Emergency equipment in place.
-
Lifting equipment in good order.
-
Excavations deeper than 1.5m benched, battered or shored.
-
Power tools plugged into RCD.
-
Shoring boxes used as per installation instructions.
-
Welding screens erected.
-
Pipes and fittings stored on level ground and choked.
-
MSDS register available.
-
Chemical and hazardous substances stored as per MSDS.
-
Material and equipment stored outside zone of influence.
Permits, Checks & Tests
-
Plant pre start completed.
-
Excavator safety pin installed.
-
Dial Before You Dig and permit to excavate completed and on site.
-
Lifting gear checked and tagged with correct colour tag.
-
Electrical tools tested and tagged.
-
Approved TMP on site.
-
Traffic control setup as per plan.
-
First aid kit items in date.
-
Fire extinguishers checked within last 6 months.
-
Confined space entry permit in place.
Signage
-
P&U and "Keep Out" sings erected.
-
SWL marked on excavator/crane.
-
Overhead signage erected and map completed.
-
Services identified and marked on ground.
-
Emergency assembly point established.
-
Emergency process, hospital and medical centre signage in place.
-
Confined spaces identified.
Environmental
Procedural
-
CEMP & EWMS available.
-
Compliant with working hours for site.
-
Heritage protection issues managed.
-
Tree protection issues managed.
-
Noise & vibration monitoring/control managed.
Spoil, sediment and water
-
Spill kits available.
-
Sediment controls installed and marked.
-
Sediment controls maintained.
-
Storm water protection in place.
-
Pumped water passing through control mechanism.
Waste and spoil
-
Waste in designated bins/areas.
-
Waste records available.
-
Spoil transportation records available.
-
Pumped water tested for pH and turbidity.
-
Contaminated waste controlled and recorded.
Site
-
Clean and tidy work area.
-
Site delineation appropriate.
-
Loads leaving site fully covered.
-
Vehicles leaving site free from dirt, mud and debris.
-
Acceptable level of restoration.
-
Construction plant clear of drip line of trees.
Quality
Procedural
-
Drawing register up to date.
-
Current drawings/documents available on site.
-
Training records up to date and available.
-
NCR, CAR & IR registers up to date and issues registered and closed out within reasonable time.
-
Variation register up to date.
-
"As Built" drawings prepared & checked.
-
Equipment calibrated & registered.
-
Drawings and documents filed appropriately.
Policy and Procedures
-
Actions from previous inspections closed out.
-
Compliant use of Daily Plant Inspection book.
-
P&U policies displayed.
-
Compliant use of HAC
-
ITP & Checklists used adequately.
-
Compliant use of Daily Site Diary
-
Authorised person viewing Hold Point and Witness Points in accordance with ITP.
-
Monthly Project Status reports completed.
Photos/Drawings
-
Add photo
-
Photo description
-
Add photo
-
Photo description
-
Add photo
-
Photo description
-
Add drawing
-
Drawing description
Inspection Findings
Follow up actions
-
Follow up actions required
Action
-
Action required.
-
Consequence
-
Date to be implemented.
-
To be implemented by.
-
Add photo if it adds value.
-
Additional comments (record positive actions also)
Inspection sign off
-
Inspection completed by.
-
Site representative.