Information

  • Audit Title: Perth Children's Hospital Subcontractor WHS Site Verification Audit

  • Conducted on

  • JH Auditor Name:

  • Subcontractor company being audited.

  • Subcontractor Representative Assisting JH Auditor (Name and Position)

  • Subcontractor Representative assisting JH Auditor (Name and Position)

  • Purpose:
    To verify on site compliance with JH safety and legislative requirements.
    Objective:
    This assessment may be used to assist with determining subcontractor compliance with the next WHS Monthly assessment.

  • CRITERIA 1

  • START CARDS<br>Start Cards are being completed by the subcontractor?<br><br>Checks to be conducted: <br>-Subcontractor is retaining Start card records<br>-Subcontractor is able to readily produce start card records<br>-Last months start cards records appears consistent with the number reported on their last months WHS returns<br>-From a sample checked they appear to be completed correctly.

  • Record any action required.

  • Add media

  • CRITERIA 2

  • TRAINING & COMPETENCY<br>Subcontractor has a system in place for ensuring workers are trained and competent?<br><br>Checks to be conducted: <br>-Identify a sample of workers who are conducting an activity that requires a VOC, Licence or Qualification<br>-Verify that the workers observed are recorded on the subcontractor training register<br>-Verify that copies if the licence, qualification or VOC is able to be produced<br>

  • Evidence 1. Record Subcontract worker name / qualification, licence or ticket which was verified.

  • Evidence 2. Record Subcontract worker name / qualification, licence or ticket which was verified.

  • Evidence 3: Record Subcontract worker name / qualification, licence or ticket which was verified.

  • Record any action required.

  • Add media

  • CRITERIA 3

  • PLANT & EQUIPMENT<br>Subcontractor has a system in place for managing plant?<br><br>Checks to be conducted:<br>-Identify a representative sample of plant being used and verify that:<br> -Prestart checks have been conducted for each item<br> -Each item of plant is recorded on the subcontractor register<br> -Service and inspection records are being maintained for each item of plant.

  • Evidence 1: Record details of make of plant, model, and plant sticker number.

  • Evidence 2. Record details of make of plant, model, and plant sticker number.

  • Evidence 3. Record details of make of plant, model, and plant sticker number.

  • Record any action required

  • Add media

  • CRITERIA 4

  • CHEMICAL MANAGEMENT<br>Subcontractor has Chemical Management Arrangements in place.<br><br>Checks to be conducted<br>- Identify a minimum of 3 chemicals on site being used and verify:<br> -Each chemical is listed on the subcontractor chemical register<br> -MSDS is dated within the last 5 years and is available for each chemical<br> -Chemical Application Approval forms have been completed for each chemical<br> -Chemical storage area is adequate in terms of ventilation, security, spill response etc.

  • Evidence 1. Record name of chemical verified:

  • Evidence 2. Record name of chemical verified.

  • Evidence 3. Record name of chemical verified.

  • Record any action required.

  • Add media

  • CRITERIA 5

  • ELECTRICAL EQUIPMENT <br>Subcontractor has a system in place for maintaining electrical equipment?<br><br>Checks to be conducted:<br>-Select 5 pieces of electrical equipment and verify:<br> - Equipment is tagged and appears in good working order<br> - Equipment is recorded on the subcontractor electrical register<br> - Electrical register contains fields which meet JH requirements

  • Evidence 1: Describe the type of electrical equipment inspected and record the tag number.

  • Evidence 2: Describe the type of electrical equipment inspected and record the tag number.

  • Evidence 3: Describe the type of electrical equipment inspected and record the tag number.

  • Evidence 4: Describe the type of electrical equipment inspected and record the tag number.

  • Evidence 5: Describe the type of electrical equipment inspected and record the tag number.

  • Record any action required.

  • Add media

  • CRITERIA 6

  • FALL PREVENTION<br>Subcontractor has a system in place for maintaining fall prevention equipment.<br><br>Checks to be conducted:<br>-Select a minimum of 3 items of fall prevention equipment and verify that:<br> - Each item is listed on the fall equipment register<br> - Inspection Records for each item of equipment are being kept<br> - Equipment selected appears in good working order and there are suitable storage arrangements in place<br> - Equipment is being correctly worn and used by workers observed.

  • Evidence 1: Record the following: Make, type and serial number of the fall prevention equipment verified.

  • Evidence 2: Record the following: Make, type and serial number of the fall prevention equipment verified.

  • Evidence 3: Record the following: Make, type and serial number of the fall prevention equipment verified.

  • Record any action required.

  • Add media

  • CRITERIA 7

  • LIFTING EQUIPMENT<br> Subcontractor has a system in place for the maintaining of lifting equipment.<br><br>Checks to be conducted:<br>-Select a minimum of 3 items of lifting equipment and verify:<br> - Each item is listed on the lifting equipment register<br> - Copies of lifting equipment inspection testing certificates are being kept<br> - Lifting equipment inspected is tagged and appears in good working order

  • Evidence 1: Record the type of lifting item inspected, including serial number.

  • Evidence 2: Record the type of lifting item inspected, including serial number.

  • Evidence 3: Record the type of lifting item inspected, including serial number.

  • Record any action required.

  • Add media

  • CRITERIA 8

  • RISK MANAGEMENT<br>Subcontractor has risk management process in place.<br><br>Checks to be conducted:<br>-Identify a minimum of 3 activities and verify:<br> - A TRA is in place for the activity<br> - All workers involved in the activity have signed onto the TRA<br> - The work is being undertaken in accordance with the TRA<br>

  • Evidence 1: Record the name (title) of the TRA, date prepared and TRA number.

  • Evidence 2: Record the name (title) of the TRA, date prepared and TRA number.

  • Evidence 3: Record the name (title) of the TRA, date prepared and TRA number.

  • Record any action required

  • Add media

  • The audit is now completed. Ensure all actions required are communicated and assigned to the subcontractor. Actions should be recorded in JHET to enable them to be maintained on a central register until closed and verified.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.