POWER TOOLS & EQUIPMENT
-
Generator 1 by CB3
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
Generator 2 By CB2
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
Generator 3 by CB1
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
ADMIN Building
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
CB1 Building
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
CB2 Building
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
CB3 Building
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
CB4 Building
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
CB5 Building. (Alkimos Only)
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
LIBRARY Building
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
-
CAB Building
-
Leads inspected were all tagged in date?
-
Tools inspected were all tagged in date?
-
All items inspected appears in good condition?
TEMPORARY POWER
-
1. The first main incoming power board is secure?
-
2. The first incoming power board is tagged in date?
-
3. The compound temporary power board is secure?
-
4. The site compound power board is tagged in date?
-
5. The site compound power board has external isolators for emergency use?
-
6. The temporary power cabling has "Temporary Power" labelling fitted?
-
7. The main on site temporary power board is tagged in date?
-
8. The temporary power cabling is installed safety off the ground as applicable?
-
9. The temporary site power distribution boards are tagged in date?
-
10. The power leads into the temporary power boards are safely entering the board?
Sign Off
-
11.2 - Project Managers signature