Post Site Work
-
Has all equipment been removed from the site?
-
Have all open holes/bores/underground works been recapped/finished at surface?
-
Has all waste, including drums and bins, been removed from the site?
-
Does the site appear to be re-instated to the condition prior to works?
-
Has the site tenant been notified of completion of the works?
-
Have all signed site safety induction checklists been received?
-
Other?
-
Actions arising from check (if any):
-
Signed PoMC Representative:
-