Information
-
Project No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Substantial Completion Date for Pinnacle
-
Substantial Completion Date for Overall Project
1. Wall Alignment (Horizontal and Vertical)
-
Barriers inhibiting access?
-
Monitoring Required
-
Maintenance Required by Pinnacle Design/Build
-
Client Notification and Maintenance Required by others<br>
-
Facing Alignment
- bulging
- settlement
- acceptable
-
Satisfactory
-
Photos of Wall Alignment
-
Additional Information
2. Grading in Front and behind
-
Barriers inhibiting access?
-
Monitoring Required
-
Maintenance Required by Pinnacle Design/Build
-
Client Notification and Maintenance Required by others<br>
-
Satisfactory
-
Photos
-
Additional Information
3. Drainage Pipe Performance
-
Barriers inhibiting access?
-
Monitoring Required
-
Maintenance Required by Pinnacle Design/Build
-
Client Notification and Maintenance Required by others<br>
-
Photos
-
Additional Information
4. Support of Existing Structures
-
Barriers inhibiting access?
-
Monitoring Required
-
Maintenance Required by Pinnacle Design/Build
-
Client Notification and Maintenance Required by others<br>
-
Satisfactory
-
Photos
-
Additional Information
5. Wall Color
-
Barriers inhibiting access?
-
Monitoring Required
-
Maintenance Required by Pinnacle Design/Build
-
Client Notification and Maintenance Required by others<br>
-
Face Staining
-
Satisfactory
-
Photos
-
Additional Information
6. Concrete Facing Units
-
Barriers inhibiting access?
-
Monitoring Required
-
Maintenance Required by Pinnacle Design/Build
-
Client Notification and Maintenance Required by others<br>
-
Satisfactory
-
Photos
-
Additional Information
Facing Condition
-
spalling
-
cracking
-
impacts
-
corrosion
-
Vegetation encroachment (are there trees/shrubs that may cause potential damage to the structure / surfacing
-
missing or damaged elements
-
Satisfactory
-
Photos
-
Additional Information
7. Site Drainage and Erosion
-
Barriers inhibiting access?
-
Monitoring Required
-
Maintenance Required by Pinnacle Design/Build
-
Client Notification and Maintenance Required by others<br>
-
Satisfactory
-
Photos
-
Additional Information
-
Drainage Swale (functioning as constructed)
-
Toe slopes
Drainage Outlets
-
Visible
-
Condition
-
Functioning
-
Flowing
8. Cap Units
-
Barriers inhibiting access?
-
Monitoring Required
-
Maintenance Required by Pinnacle Design/Build
-
Client Notification and Maintenance Required by others<br>
-
Satisfactory
-
Photos
-
Additional Information
Structure
-
Barriers inhibiting access?
-
Erosion
- Excessive
- Threatening Structure
- N/A
-
Vegetation encroachment (are there trees/shrubs that may cause potential damage to the structure / surfacing
Site Observations
-
Any evidence of excavation in/around reinforced zone
-
Are irrigation lines and / or materials stockpiles located in exclusion zone?
-
Is there new construction that may interfere or damage structural elements(i.e. geogrids etc.)
-
Is heavy equipment parked on the structure or is there evidence that heavy equipment was stored there in the past?
-
Are materials stored on the structure or is there evidence that materials were stored there in the past?
-
Vegetation encroachment (are there trees/shrubs that may cause potential damage to the structure / surfacing
-
Erosion
- Excessive
- Threatening Structure
- N/A
-
curbs, pavement/sidewalks inspected carefully for settlement, misalignment, cracking, depressions